  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Alberta's auditor general granted extra $1M for health procurement probe

Alberta's auditor general granted extra $1M for health procurement probe
His investigation began earlier this year as a result of allegations made by the former head of Alberta Health Services, the provincial health authority.

Alberta's auditor general granted extra $1M for health procurement probe

RCMP identify second victim of Banff rockfall as man, 33, from Surrey, B.C.

RCMP identify second victim of Banff rockfall as man, 33, from Surrey, B.C.
The second deceased person has previously been identified as 70-year-old Jutta Hinrichs, a retired university professor from Calgary.

RCMP identify second victim of Banff rockfall as man, 33, from Surrey, B.C.

Canada signs security and defence partnership with Europe

Canada signs security and defence partnership with Europe
The agreement commits them to collaborate more on defence and is a step toward Canada participating in the continent's massive new defence procurement program, known as ReArm Europe.

Canada signs security and defence partnership with Europe

Canada starts busing citizens out of Israel days after allies began

Canada starts busing citizens out of Israel days after allies began
Last Thursday, Anand announced that Canadian consular officials would be standing by at border crossings to help citizens who fled Israel or Iran to reach Canada through commercial means.

Canada starts busing citizens out of Israel days after allies began

Police in B.C. say suspect known as 'Mr. X' in 1985 Air India bombing is dead

Police in B.C. say suspect known as 'Mr. X' in 1985 Air India bombing is dead
The bomb on Air India Flight 182 exploded over the Atlantic Ocean, killing everyone on board, while a second suitcase bomb exploded before being transferred onto an Air India jet, killing two baggage handlers in Tokyo's Narita Airport. 

Police in B.C. say suspect known as 'Mr. X' in 1985 Air India bombing is dead

Mark Carney names Kirsten Hillman chief negotiator with U.S.

Mark Carney names Kirsten Hillman chief negotiator with U.S.
Prime Minister Mark Carney's office confirms Hillman has been named to the position, making her U.S. Trade Representative Jamieson Greer's opposite number in the bilateral trade talks.

Mark Carney names Kirsten Hillman chief negotiator with U.S.