BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Carney to speak with media after cabinet gathers to plan for new Parliament

Carney to speak with media after cabinet gathers to plan for new Parliament
Prime Minister Mark Carney is set to take questions from reporters on Parliament Hill this evening after holding a secretive, two-day retreat with his new cabinet in Gatineau, Que.

Carney to speak with media after cabinet gathers to plan for new Parliament

Float plane crash near Powell River, B.C., injures three

Float plane crash near Powell River, B.C., injures three
Three people have been injured in a float plane crash along the British Columbia coastline.

Float plane crash near Powell River, B.C., injures three

Port says dredging of Vancouver's Burrard Inlet underway, a project touted by Carney

Port says dredging of Vancouver's Burrard Inlet underway, a project touted by Carney
The Vancouver Fraser Port Authority says preliminary work on a plan to dredge Burrard Inlet to accommodate fully loaded oil tankers is now underway

Port says dredging of Vancouver's Burrard Inlet underway, a project touted by Carney

Canadians have more trust in Carney than they did in Trudeau: poll

Canadians have more trust in Carney than they did in Trudeau: poll
Canadians have more trust in Prime Minister Mark Carney now than they did in former prime minister Justin Trudeau after he was first elected, a new poll suggests.

Canadians have more trust in Carney than they did in Trudeau: poll

Western premiers meet in Yellowknife to talk trade, energy and Arctic security

Western premiers meet in Yellowknife to talk trade, energy and Arctic security
Premiers from Western Canada are to meet Wednesday to kick off a two-day conference in Yellowknife.

Western premiers meet in Yellowknife to talk trade, energy and Arctic security

Crown argues hockey player faking memory loss in testifying at ex-teammates' trial

Crown argues hockey player faking memory loss in testifying at ex-teammates' trial
A former member of Canada's world junior hockey team is pretending not to remember details that could be damaging to five of his ex-teammates currently on trial for sexual assault, prosecutors argued Wednesday.

Crown argues hockey player faking memory loss in testifying at ex-teammates' trial