BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Canada's dairy industry says tariffs less scary than threats to supply management

Canada's dairy industry says tariffs less scary than threats to supply management
Members of Canada's dairy industry say they're less worried about the threat of steep U.S. tariffs than about a looming battle over supply management. U.S. President Donald Trump has threatened to impose what he calls "reciprocal" tariffs on Canadian dairy, saying they're a response to Canada's 250 per cent duty on U.S. dairy imports.

Canada's dairy industry says tariffs less scary than threats to supply management

Trump says he will double tariffs on Canadian steel, aluminum imports

Trump says he will double tariffs on Canadian steel, aluminum imports
Trump said 50 per cent tariffs will be placed on Canadian steel and aluminum on Wednesday. In a post on social media, he called Canada "ONE OF THE HIGHEST TARIFFING NATIONS ANYWHERE IN THE WORLD."

Trump says he will double tariffs on Canadian steel, aluminum imports

Resort confirms Kicking Horse gondola fell one metre to ground, 8 on board

Resort confirms Kicking Horse gondola fell one metre to ground, 8 on board
The owner of Kicking Horse Mountain Resort in Golden has confirmed eight people were aboard a gondola that fell to the ground Monday morning. Resorts of the Canadian Rockies says its patrol team and first responders were immediately dispatched after it happened around 9:20 a.m., but no one was seriously injured in the incident.

Resort confirms Kicking Horse gondola fell one metre to ground, 8 on board

Incoming prime minister Mark Carney says he has put his assets in a blind trust

Incoming prime minister Mark Carney says he has put his assets in a blind trust
Mark Carney's leadership campaign says he has given a "full and robust conflict of interest management plan" to the country's ethics commissioner. In a media statement, the campaign says that as part of that plan, Carney has divested all of his assets other than personal real estate into a blind trust.

Incoming prime minister Mark Carney says he has put his assets in a blind trust

B.C. Mountie tells hearing that 'dark humour' in group chats was to relieve stress

B.C. Mountie tells hearing that 'dark humour' in group chats was to relieve stress
A British Columbia RCMP officer says he and fellow officers used "dark humour" as a way to vent their frustrations, but he's not proud of his statements and thinks it's unfortunate that the police group chats were revealed through a complaint. Port Coquitlam RCMP Const. Ian Solven testified Monday in Surrey at a code of conduct hearing involving him and two other officers.

B.C. Mountie tells hearing that 'dark humour' in group chats was to relieve stress

Gondola falls near base of lift at Kicking Horse ski resort near Golden

Gondola falls near base of lift at Kicking Horse ski resort near Golden
The lifts at Kicking Horse Mountain Resort in southeastern British Columbia were shut down Monday after a gondola cabin fell to the ground. Photos online show the cabin on its side near the base of a lift, suggesting it may have fallen a few metres.

Gondola falls near base of lift at Kicking Horse ski resort near Golden