BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Liberal leadership hopeful Ruby Dhalla says she wants a translator for French debate

Liberal leadership hopeful Ruby Dhalla says she wants a translator for French debate
Liberal leadership candidate Ruby Dhalla says that while she's still working on her French skills, she plans to ask for a translator to help her in the party's upcoming French-language debate. Dhalla is one of the five leadership candidates who will face off in two debates in Montreal later this month, one in French and another in English.

Liberal leadership hopeful Ruby Dhalla says she wants a translator for French debate

Claims process for First Nations child welfare class action opens in March, AFN says

Claims process for First Nations child welfare class action opens in March, AFN says
The Assembly of First Nations says children and their families who lived under Canada's First Nations child welfare system from 1991 to 2022 can apply for a class action settlement starting in March. National Chief Cindy Woodhouse Nepinak says the settlement is an acknowledgment of the harms First Nations people experienced under a "racist system that has broken so many lives and families."

Claims process for First Nations child welfare class action opens in March, AFN says

Singh promises 100% tariffs on Tesla, revival of electric vehicle incentive program

Singh promises 100% tariffs on Tesla, revival of electric vehicle incentive program
NDP Leader Jagmeet Singh says Canada should charge 100 per cent tariffs on Tesla vehicles for as long as its trade war with the United States continues. He also says in a new release today that a government led by him would revive the federal government's incentive program for electric vehicle purchases.

Singh promises 100% tariffs on Tesla, revival of electric vehicle incentive program

Pedestrian killed in crash in Abbotsford linked to impaired driving

Pedestrian killed in crash in Abbotsford linked to impaired driving
A male pedestrian is dead after he was struck by what police are describing as an impaired driver in Abbotsford..... Police say the crash happened this morning in the 30000 block of Harris Road, where a white Dodge pickup truck had struck a power pole with enough force to shear off the pole.

Pedestrian killed in crash in Abbotsford linked to impaired driving

Two injured in unprovoked attack at business in Surrey

Two injured in unprovoked attack at business in Surrey
Police in Surrey are on the lookout for a suspect involved in two unprovoked attacks in the city that sent one person to hospital. Surrey police say the attack took place at an unspecified business on 120 Street, where the suspect began by physically assaulting a staff member.

Two injured in unprovoked attack at business in Surrey

Trump’s invasion threats violate international law: Canadian ambassador

Trump’s invasion threats violate international law: Canadian ambassador
Canada's ambassador to France says United States President Donald Trump's invasion threats violate international law. Trump has said he wouldn’t rule out using military force to take over Greenland, which is part of Denmark.

Trump’s invasion threats violate international law: Canadian ambassador