BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Police say YouTuber caught speeding on Vancouver Island loses car for a week

Police say YouTuber caught speeding on Vancouver Island loses car for a week
Mounties on Vancouver Island say a man who described himself as a YouTube influencer had his vehicle impounded and was fined $368 for speeding. Police say an unmarked BC Highway Patrol officer was working Sunday in Lantzville when he heard an "excessively loud" vehicle accelerate from a stoplight on Highway 19.

Police say YouTuber caught speeding on Vancouver Island loses car for a week

California builders say few alternatives to Canadian timber, despite tariff threat

California builders say few alternatives to Canadian timber, despite tariff threat
California homebuilders say they have few options but to keep buying Canadian lumber, even if it's hit with 25 per cent tariffs, as they rebuild thousands of homes destroyed by devastating wildfires in Los Angeles.

California builders say few alternatives to Canadian timber, despite tariff threat

B.C. investigates 'significant' opioid diversion, including international trafficking

B.C. investigates 'significant' opioid diversion, including international trafficking
A recent B.C. Ministry of Health document says a "significant portion" of opioids prescribed by doctors and pharmacists are being diverted and that prescribed alternatives are being trafficked provincially, nationally and internationally.

B.C. investigates 'significant' opioid diversion, including international trafficking

2 arrested in catalytic converter theft

2 arrested in catalytic converter theft
Mounties in Burnaby say two women have been arrested after stealing a catalytic converter from a van in a parking lot in the area of Brighton Avenue and Lougheed Highway. They say that on January 22nd, officers responded to reports of the women underneath the vehicle, but the pair left the scene before they arrived. 

2 arrested in catalytic converter theft

Talk of changing Vancouver's supportive housing policy has organizations on edge

Talk of changing Vancouver's supportive housing policy has organizations on edge
Mayor Ken Sim announced last month that he would be putting forward a proposal to pause construction of net new supportive housing units in Vancouver, arguing that the city needs to focus on updating its current stock, while supply in other parts of the region increases.

Talk of changing Vancouver's supportive housing policy has organizations on edge

Police ask for help in probe of B.C. woman's death in fall from a truck

Police ask for help in probe of B.C. woman's death in fall from a truck
The RCMP's major crime unit is asking for the public's help in investigating the death of a woman almost a month ago in Trial. Police say 38-year-old Laura Morrison was the front passenger in a 2023 white Ford F-150 late on Jan. 9 when she reportedly fell from the moving vehicle. 

Police ask for help in probe of B.C. woman's death in fall from a truck