BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Bridge over Okanagan Lake in B.C. reopens after bomb scare, fire in van

Bridge over Okanagan Lake in B.C. reopens after bomb scare, fire in van
Police have reopened a bridge across Okanagan Lake in the B.C. Interior after an explosives scare that shut it down for about 11 hours. Officers say the incident began early Monday morning when a man parked a white panel van across multiple lanes of the William R. Bennett Bridge and posted online remarks about the contents.

Bridge over Okanagan Lake in B.C. reopens after bomb scare, fire in van

Kelowna Bridge has reopens after an overnight closure prompted by a call about a person in crisis

Kelowna Bridge has reopens after an overnight closure prompted by a call about a person in crisis
Police in Kelowna say the William Bennet Bridge has reopened after an overnight closure that was prompted by a call about a person in crisis. RCMP say officers had responded at about 3:45 a-m, finding the person had parked a vehicle across the eastbound lanes of the bridge.

Kelowna Bridge has reopens after an overnight closure prompted by a call about a person in crisis

Two people are facing charges in Prince George after police seized drugs and guns during an attempted traffic stop

Two people are facing charges in Prince George after police seized drugs and guns during an attempted traffic stop
Two people are facing charges in Prince George after police seized drugs and guns during an attempted traffic stop. R-C-M-P say officers were patrolling along Highway 97 last week when they tried to stop a driver who they allegedly saw committing motor vehicle infractions.

Two people are facing charges in Prince George after police seized drugs and guns during an attempted traffic stop

One dead after a single-vehicle rollover crash in Delta

One dead after a single-vehicle rollover crash in Delta
One person is dead after a single-vehicle rollover crash in Metro Vancouver. Police in Delta say it happened last night along Highway 99, near the exit for Highway 17, where a pick-up truck crashed into a barrier before rolling onto its roof.

One dead after a single-vehicle rollover crash in Delta

Ford's decision to speed up alcohol sales expansion will cost province $612M: report

Ford's decision to speed up alcohol sales expansion will cost province $612M: report
Premier Doug Ford's decision to speed up the rollout of alcohol sales in corner stores — which first sparked early election speculation last spring — will cost the province more than $600 million, Ontario's budget watchdog said Monday. That's nearly three times the amount the Progressive Conservative government said it would cost to accelerate the timeline.

Ford's decision to speed up alcohol sales expansion will cost province $612M: report

Canada stops letting cross-border hikers enter B.C. via Pacific Crest Trail

Canada stops letting cross-border hikers enter B.C. via Pacific Crest Trail
The agency has announced it will stop issuing permits for people to enter Canada on the Pacific Crest Trail, saying the move helps enhance border security and allows for compliance monitoring of those using the hiking and horse-riding trail.

Canada stops letting cross-border hikers enter B.C. via Pacific Crest Trail