Tuesday, June 30, 2026
ADVT 
National

BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Edmonton school board, union for support staff head back to bargaining table

Edmonton school board, union for support staff head back to bargaining table
The union representing school support workers in Edmonton says it has returned to the bargaining table with the city's public school board. Some 3,000 staff, from educational assistants to cafeteria workers, have been on picket lines since Jan. 13 over a wage dispute with the Edmonton Public School Board.

Edmonton school board, union for support staff head back to bargaining table

Escaped prison inmate arrested in Saskatchewan after three weeks

Escaped prison inmate arrested in Saskatchewan after three weeks
RCMP say an inmate has been arrested three weeks after he escaped from a federal prison in Saskatchewan. Mounties say they were searching for Glen Halkett in the Rosthern, Sask., area and spotted him as a passenger in a vehicle with three others. 

Escaped prison inmate arrested in Saskatchewan after three weeks

Six migrants found crossing border on foot in freezing temperatures: Manitoba RCMP

Six migrants found crossing border on foot in freezing temperatures: Manitoba RCMP
Mounties in Manitoba say six people from multiple countries were caught last week trying to illegally cross into Canada from the United States. Police say the group was spotted from the air crossing the border on foot near Emerson on Jan. 14. 

Six migrants found crossing border on foot in freezing temperatures: Manitoba RCMP

Vancouver mayor proposes pause on new supportive housing in Downtown Eastside

Vancouver mayor proposes pause on new supportive housing in Downtown Eastside
Vancouver Mayor Ken Sim has unveiled a plan to revitalize the city's troubled Downtown Eastside, including pausing the construction of net new supportive housing units. Sim told a Save Our Streets forum, held by a coalition of groups concerned about crime and public safety in B.C., that the proposal is one of three key policy shifts being planned to transform the Downtown Eastside.

Vancouver mayor proposes pause on new supportive housing in Downtown Eastside

U.S. tariff threat adds urgency for B.C.'s energy independence: minister

U.S. tariff threat adds urgency for B.C.'s energy independence: minister
British Columbia Energy Minister Adrian Dix says the looming threat of American tariffs raises the stakes for boosting the province's energy independence. Dix says there was urgency before the U.S. election last November, but "there's more now" as American President Donald Trump threatens to impose 25 per cent tariffs on Canadian goods.

U.S. tariff threat adds urgency for B.C.'s energy independence: minister

Victoria garbage truck driver delivers fire to fire department

Victoria garbage truck driver delivers fire to fire department
The driver of a garbage truck in Victoria is being hailed for his quick thinking when he saw smoke coming from the back compartment. The Victoria Firefighters Association posted its praise on social media saying the driver called 911 when he saw the smoke — then drove straight to the firehall. 

Victoria garbage truck driver delivers fire to fire department