Regulator lifts Trans Mountain stop-work order

Darpan News Desk The Canadian Press, 22 Jun, 2021 03:28 PM
  • Regulator lifts Trans Mountain stop-work order

A federal regulator has lifted a stop-work order on tree cutting and grass mowing along the Trans Mountain pipeline expansion project route.

Trans Mountain has now submitted a satisfactory plan to correct deficiencies in the oversight of its contractors that could pose threats to nesting birds, the Canada Energy Regulator said Tuesday in a statement.

The regulator, which enforces safety and environmental guidelines for pipeline projects, issued a stop-work order on June 3 following investigations of tree-clearing work in the suburban Vancouver area that could have impacted nesting birds.

The regulator's website outlines four incidents along the pipeline route in the Burnaby and Coquitlam areas and near Agassiz in the Fraser Valley that date back to early April when a member of the public complained about bird nest destruction and improper buffer zones.

It also investigated tree-felling work near Agassiz that destroyed a robin's nest despite the area being marked by flags as a no-cutting zone.

The regulator says the stop-work order was issued after Trans Mountain reported to it on June 2 that one of its contractor crews cleared trees and shrubs in Burnaby without company authority.

No damaged or destroyed bird nests were reported in the June 2 incident, says the regulator.

"The order requires Trans Mountain to investigate and find the root cause for why there were two incidents related to contractor oversight issues in May," the regulator said in its order.

"Trans Mountain must also be able to prove that work is being done in a way that protects the environment, and more specifically, that workers are following Trans Mountain's own procedures and mitigation practices to protect the environment and migratory birds."

The regulator says Trans Mountain's plans now include improving field procedures to protect nesting birds and increasing direct supervision of its contractors.

Trans Mountain said in a statement on Tuesday the plan it filed to the regulator includes implementing enhanced communication, supervision and training measures before restarting pipeline clearing work.

The $12.6-billion expansion project between Burnaby, B.C., and north of Edmonton will triple existing pipeline capacity to about 890,000 barrels per day of oil products, including diluted bitumen, lighter crude and refined fuel.

 

MORE National ARTICLES

Economy grew at 5.6% rate in Q1, StatCan says

Economy grew at 5.6% rate in Q1, StatCan says
The figure for the first three months of the year is better than the contraction first forecast months ago, but still represents a slowdown from the 9.6 per cent annualized growth seen over the last three months of 2020.

Economy grew at 5.6% rate in Q1, StatCan says

AstraZeneca recipients can get mRNA for 2nd dose

AstraZeneca recipients can get mRNA for 2nd dose
NACI has already said people can mix and match vaccines within the same vaccine family — so the mRNA vaccines from Pfizer and Moderna can be mixed and matched, or the viral vector vaccines from AstraZeneca and Johnson & Johnson.    

AstraZeneca recipients can get mRNA for 2nd dose

PM promises cities help to lower housing costs

PM promises cities help to lower housing costs
The cost of housing has risen across the country driven by a mix of low interest rates and demand outstripping supply as Canadians working from home look for more space.

PM promises cities help to lower housing costs

More arrests at B.C. logging blockade

More arrests at B.C. logging blockade
The Mounties say since enforcement of the court injunction began on May 17, 142 people have been arrested, at least nine of whom have been arrested more than once.

More arrests at B.C. logging blockade

B.C. COVID cases down, but stay vigilant: doctor

B.C. COVID cases down, but stay vigilant: doctor
"We have seen new outbreaks in recent days and we all need to take our precautions to prevent more," she says, adding masks will still need to be worn until about July even by people who have had two doses of vaccine because vaccines alone are not fully protective against infection.    

B.C. COVID cases down, but stay vigilant: doctor

Canada won't rush border reopening: Trudeau

Canada won't rush border reopening: Trudeau
Canada won't be rushed into reopening its border with the United States to non-essential travel, Prime Minister Justin Trudeau said Monday as new COVID-19 case counts continued to drop in much of the country.

Canada won't rush border reopening: Trudeau