Regulator lifts Trans Mountain stop-work order

Darpan News Desk The Canadian Press, 22 Jun, 2021 03:28 PM
  • Regulator lifts Trans Mountain stop-work order

A federal regulator has lifted a stop-work order on tree cutting and grass mowing along the Trans Mountain pipeline expansion project route.

Trans Mountain has now submitted a satisfactory plan to correct deficiencies in the oversight of its contractors that could pose threats to nesting birds, the Canada Energy Regulator said Tuesday in a statement.

The regulator, which enforces safety and environmental guidelines for pipeline projects, issued a stop-work order on June 3 following investigations of tree-clearing work in the suburban Vancouver area that could have impacted nesting birds.

The regulator's website outlines four incidents along the pipeline route in the Burnaby and Coquitlam areas and near Agassiz in the Fraser Valley that date back to early April when a member of the public complained about bird nest destruction and improper buffer zones.

It also investigated tree-felling work near Agassiz that destroyed a robin's nest despite the area being marked by flags as a no-cutting zone.

The regulator says the stop-work order was issued after Trans Mountain reported to it on June 2 that one of its contractor crews cleared trees and shrubs in Burnaby without company authority.

No damaged or destroyed bird nests were reported in the June 2 incident, says the regulator.

"The order requires Trans Mountain to investigate and find the root cause for why there were two incidents related to contractor oversight issues in May," the regulator said in its order.

"Trans Mountain must also be able to prove that work is being done in a way that protects the environment, and more specifically, that workers are following Trans Mountain's own procedures and mitigation practices to protect the environment and migratory birds."

The regulator says Trans Mountain's plans now include improving field procedures to protect nesting birds and increasing direct supervision of its contractors.

Trans Mountain said in a statement on Tuesday the plan it filed to the regulator includes implementing enhanced communication, supervision and training measures before restarting pipeline clearing work.

The $12.6-billion expansion project between Burnaby, B.C., and north of Edmonton will triple existing pipeline capacity to about 890,000 barrels per day of oil products, including diluted bitumen, lighter crude and refined fuel.

 

MORE National ARTICLES

Trudeau vows support after unmarked graves found

Trudeau vows support after unmarked graves found
Trudeau offered sombre words today about the remains of 215 children on the grounds of the former Kamloops Indian Residential School, calling it "heartbreaking news."    

Trudeau vows support after unmarked graves found

63 per cent of B.C. residents have one COVID shot

63 per cent of B.C. residents have one COVID shot
Officials say there has been a COVID-19 outbreak at a long-term care facility, Brookside Lodge in Surrey, where one resident and a staff member have tested positive.    

63 per cent of B.C. residents have one COVID shot

CN Rail fined $100,000 for pesticide on B.C. track

CN Rail fined $100,000 for pesticide on B.C. track
British Columbia's Conservation Officer Service says Canadian National Railway has entered a guilty plea in a Prince Rupert court for failing to obtain the needed authorization to apply pesticide along its tracks.

CN Rail fined $100,000 for pesticide on B.C. track

317 COVID cases for Friday

317 COVID cases for Friday
3,106,269 doses of Pfizer-BioNTech, Moderna and AstraZeneca COVID-19 vaccines have been administered in B.C., 160,885 of which are second doses.

317 COVID cases for Friday

Canada's First Program in Sikh Studies

Canada's First Program in Sikh Studies
With over 700,000 Sikhs in the country, it is no surprise that the time has come to reflect and represent Sikhism in the education system. Hoping to accomplish just this, the University of Calgary is soon slated to launch the nation’s first-of-its-kind Sikh Studies program, spearheaded by a dynamic duo. 

Canada's First Program in Sikh Studies

DARPAN 10 with Mr Manish: Consul General of India in Vancouver

DARPAN 10 with Mr Manish: Consul General of India in Vancouver
I was very excited at the thought of bringing my contribution to further our relationship between India and the five important provinces in Western Canada, namely British Columbia, Saskatchewan, Alberta, Yukon and Northwest Territories.

DARPAN 10 with Mr Manish: Consul General of India in Vancouver