Darpan News Desk The Canadian Press, 02 May, 2024 01:13 PM
  • Saskatchewan's Boundary dam carbon capture project underperforms, report says

"We don't think carbon capture works as well as industry and promoters claim," said David Schissel, an analyst who wrote the report for the Institute for Energy Economics and Financial Analysis, an international non-profit agency.

"We don't think it's a good use of money to keep coal-fired power plants running."

Schissel looked at data from Sask Power's Boundary Dam project, a coal-fired power plant in southeast Saskatchewan that began capturing carbon dioxide emissions in the fall of 2014. 

Proponents originally said the plant would capture up to 90 per cent of the plant's carbon emissions. That would amount to about a million tonnes of climate-changing carbon dioxide a year — the rough equivalent of emissions from 200,000 cars.   

That goal has never been reached, said Schissel. 

When all the plant's emissions are factored in, including flue gas that is simply vented, the average capture rate is 57 per cent, he said.

A 2022 report delivered to an international conference on carbon capture backs up the findings. 

"(The project) has not sustained the design rate beyond a dedicated capacity demonstration completed in 2015," says the report from the International CCS Knowledge Centre in Regina. 

The report says capture is limited by both technical issues and the demand for carbon dioxide from the energy industry, which uses the gas to extract more oil from depleting reserves. 

The plant's capture rate has improved, although it's still short of the million-tonne mark.  

Knowledge Centre spokesman Grady Semmens said Schissel's analysis is "generally correct."

He said the plant has managed to keep nearly six million tonnes of carbon dioxide out of the atmosphere. As well, he said almost all the CO2 from the emissions that are sent through the capture facility is separated out.

"For a variety of technical and economic reasons ... the (Boundary Dam) facility has not been run at full capacity, which has impacted the overall volume of CO2 captured over the last 10 years," Semmens wrote in an email. "This does not mean the project has not been successful.

"It has provided valuable experience and lessons that we are now actively applying to the next generation of CCS projects."

SaskPower spokesman Scott McGregor said the facility continues to improve. He said the equipment was online for almost the entire first three months of 2024 — its best performance yet.

"The knowledge we’ve gained at our (carbon capture) facility has also made SaskPower a resource for development of (such) projects in a wide range of industries outside of power generation, such as cement manufacturing, oil and gas production and chemical processing," he said in an email.

But Schissel said to live up to advocates' promises, carbon capture has to work nearly perfectly all the time. 

"If you're going to try to reduce greenhouse gas emissions by capturing CO2, you've got to capture almost all the emissions and you've got to do it year in and year out for decades."

"Carbon capture hasn't done what its proponents claimed it would do."

Other carbon capture projects have yet to reach their stated goals.

Since 2015, Shell's Quest project near Edmonton has stored nine million tonnes of CO2 at a lower-than-anticipated cost. But its capture rate of 77 per cent remains below the 90 per cent originally announced.

On Wednesday, Capital Power CEO Avik Dey said the company would no longer pursue its $2.4-billion carbon capture project at its Genesee power plant.

"Fundamentally, the economics just don't work," he told analysts in a conference call. "Hopefully, the technology will improve, and we can revisit this when the economics improve.

"What it really is, is the technology improving so the costs come down. How do you actually build the kit so you have higher efficacy and capture rates while bringing down the capture costs?"

Alberta's oilsands producers have estimated the cost of the first phase of carbon capture for the industry at $16 billion. 

Schissel said carbon capture can be worthwhile in some circumstances, especially at a smaller scale. He said it remains questionable if the technology can work at the level proponents suggest and asks whether it's the most cost-effective way to reduce emissions at large operations.

"We may find out in 20 years that we didn't capture as much CO2 as we needed to and we wasted a lot of money that could have been better spent."

MORE National ARTICLES

B.C. to end state of emergency as wildfire risk winds down

B.C. to end state of emergency as wildfire risk winds down
The British Columbia government says it is ending the state of emergency imposed last month when thousands of residents were chased out of their homes by wildfires.  The government says in a statement the wildfire risk is diminishing in much of the province as temperatures cool, allowing most residents to return home. 

B.C. to end state of emergency as wildfire risk winds down

DNA match in Ibrahim Ali murder case as exact as identical twins, B.C. court is told

DNA match in Ibrahim Ali murder case as exact as identical twins, B.C. court is told
An RCMP expert testifying at Ibrahim Ali's murder trial told the court she has never seen a DNA match as close as the one between the suspect and samples found on his alleged victim — except for DNA matches between identical twins. Forensic biologist Christine Crossman said police investigators were very thorough in their collection and testing of genetic samples from the body of the 13-year-old girl, whose identity is protected by a publication ban.

DNA match in Ibrahim Ali murder case as exact as identical twins, B.C. court is told

Ex-B.C. police chief to investigate release of suspect before Chinatown stabbing

Ex-B.C. police chief to investigate release of suspect before Chinatown stabbing
Former Abbotsford police chief Bob Rich has been appointed to look into the release of a man from British Columbia's psychiatric hospital before the man allegedly stabbed three people in Vancouver's Chinatown. Premier David Eby said Thursday that he has read the BC Review Board report on the accused and wants Rich to determine how the man could have been released, despite being a "really significant danger to the public." 

Ex-B.C. police chief to investigate release of suspect before Chinatown stabbing

Federal government will remove GST on new rental housing builds, senior source says

Federal government will remove GST on new rental housing builds, senior source says
A senior government source says Ottawa is planning to remove the G-S-T on construction of new rental apartment buildings. The source, who spoke on the condition of anonymity, says Prime Minister Justin Trudeau is expected to make the announcement today as he wraps up a three-day Liberal caucus retreat in London, Ontario.

Federal government will remove GST on new rental housing builds, senior source says

B.C. Sikh referendum will ask if Indian diplomat was responsible for Nijjar killing

B.C. Sikh referendum will ask if Indian diplomat was responsible for Nijjar killing
The group Sikhs for Justice, which has been staging a series of non-binding votes in several countries on the independence issue, says the first stage of balloting in B.C. on Sunday attracted more than 135,000 voters. It says the second stage will be held on Oct. 29 and will add a second question about whether High Commissioner Sanjay Verma was responsible for the "assassination" of Hardeep Singh Nijjar.

B.C. Sikh referendum will ask if Indian diplomat was responsible for Nijjar killing

All former youth in care in B.C. now eligible for education tuition waivers: minister

All former youth in care in B.C. now eligible for education tuition waivers: minister
British Columbia has expanded its tuition waiver program to include all former youth in government care enrolling in post-secondary education. Selina Robinson, post-secondary education and future skills minister, says the program is no longer capped at the student's 27th birthday.

All former youth in care in B.C. now eligible for education tuition waivers: minister