  • Saskatchewan's Boundary dam carbon capture project underperforms, report says

"We don't think carbon capture works as well as industry and promoters claim," said David Schissel, an analyst who wrote the report for the Institute for Energy Economics and Financial Analysis, an international non-profit agency.

"We don't think it's a good use of money to keep coal-fired power plants running."

Schissel looked at data from Sask Power's Boundary Dam project, a coal-fired power plant in southeast Saskatchewan that began capturing carbon dioxide emissions in the fall of 2014. 

Proponents originally said the plant would capture up to 90 per cent of the plant's carbon emissions. That would amount to about a million tonnes of climate-changing carbon dioxide a year — the rough equivalent of emissions from 200,000 cars.   

That goal has never been reached, said Schissel. 

When all the plant's emissions are factored in, including flue gas that is simply vented, the average capture rate is 57 per cent, he said.

A 2022 report delivered to an international conference on carbon capture backs up the findings. 

"(The project) has not sustained the design rate beyond a dedicated capacity demonstration completed in 2015," says the report from the International CCS Knowledge Centre in Regina. 

The report says capture is limited by both technical issues and the demand for carbon dioxide from the energy industry, which uses the gas to extract more oil from depleting reserves. 

The plant's capture rate has improved, although it's still short of the million-tonne mark.  

Knowledge Centre spokesman Grady Semmens said Schissel's analysis is "generally correct."

He said the plant has managed to keep nearly six million tonnes of carbon dioxide out of the atmosphere. As well, he said almost all the CO2 from the emissions that are sent through the capture facility is separated out.

"For a variety of technical and economic reasons ... the (Boundary Dam) facility has not been run at full capacity, which has impacted the overall volume of CO2 captured over the last 10 years," Semmens wrote in an email. "This does not mean the project has not been successful.

"It has provided valuable experience and lessons that we are now actively applying to the next generation of CCS projects."

SaskPower spokesman Scott McGregor said the facility continues to improve. He said the equipment was online for almost the entire first three months of 2024 — its best performance yet.

"The knowledge we’ve gained at our (carbon capture) facility has also made SaskPower a resource for development of (such) projects in a wide range of industries outside of power generation, such as cement manufacturing, oil and gas production and chemical processing," he said in an email.

But Schissel said to live up to advocates' promises, carbon capture has to work nearly perfectly all the time. 

"If you're going to try to reduce greenhouse gas emissions by capturing CO2, you've got to capture almost all the emissions and you've got to do it year in and year out for decades."

"Carbon capture hasn't done what its proponents claimed it would do."

Other carbon capture projects have yet to reach their stated goals.

Since 2015, Shell's Quest project near Edmonton has stored nine million tonnes of CO2 at a lower-than-anticipated cost. But its capture rate of 77 per cent remains below the 90 per cent originally announced.

On Wednesday, Capital Power CEO Avik Dey said the company would no longer pursue its $2.4-billion carbon capture project at its Genesee power plant.

"Fundamentally, the economics just don't work," he told analysts in a conference call. "Hopefully, the technology will improve, and we can revisit this when the economics improve.

"What it really is, is the technology improving so the costs come down. How do you actually build the kit so you have higher efficacy and capture rates while bringing down the capture costs?"

Alberta's oilsands producers have estimated the cost of the first phase of carbon capture for the industry at $16 billion. 

Schissel said carbon capture can be worthwhile in some circumstances, especially at a smaller scale. He said it remains questionable if the technology can work at the level proponents suggest and asks whether it's the most cost-effective way to reduce emissions at large operations.

"We may find out in 20 years that we didn't capture as much CO2 as we needed to and we wasted a lot of money that could have been better spent."

MORE National ARTICLES

Explosion in Prince George

Explosion in Prince George
A large explosion at an abandoned building in downtown Prince George, B.C., has sent several people to hospital, RCMP say. The blast happened about 7 a.m. Tuesday.

Explosion in Prince George

West Edmonton Mall locked down as 3 seriously injured in shooting: police

West Edmonton Mall locked down as 3 seriously injured in shooting: police
Three men were injured in a shooting Monday night at West Edmonton Mall, where those inside were locked down in stores and restaurants for two hours. Police said in a news release that the men were taken to hospital with serious but non-life threatening injuries.

West Edmonton Mall locked down as 3 seriously injured in shooting: police

Kelowna teacher charged with child luring

Kelowna teacher charged with child luring
A Kelowna teacher has been charged with luring a child after police investigated allegations of inappropriate communications with a student. Kelowna R-C-M-P say Jeffrey Allen Jennens was scheduled to appear in court yesterday.

Kelowna teacher charged with child luring

Critical firefighting equipment being moved or stolen, says BC Wildfire Service

Critical firefighting equipment being moved or stolen, says BC Wildfire Service
BC Wildfire Service says critical equipment used to fight some of the province's devastating blazes has been moved and sometimes stolen, in one case three times. The fire service says the pumps, sprinklers, hoses and ATVs that have been taken in the North Shuswap area are "critically impacting" the effectiveness of structural protection.

Critical firefighting equipment being moved or stolen, says BC Wildfire Service

Feds to consider caps on int'l study permits as housing crisis grows: Fraser

Feds to consider caps on int'l study permits as housing crisis grows: Fraser
Canada is looking to crack down on unscrupulous schools that are cashing in on the big bucks of international student tuition fees without putting any thought into where those students are going to live, Housing Minister Sean Fraser said Monday.

Feds to consider caps on int'l study permits as housing crisis grows: Fraser

Two charged in Nanaimo arson

Two charged in Nanaimo arson
Two men are facing charges after a fire in downtown Nanaimo. R-C-M-P say it happened on Saturday night when a patrol officer saw smoke and flames coming from a commercial building.

Two charged in Nanaimo arson