Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

Amidst inflation which mortgage to chose?

Amidst inflation which mortgage to chose?
It is a conundrum that has faced countless homebuyer in recent years -- choosing a fixed- or variable-rate mortgage. That question has taken on even more significance following the Bank of Canada's recent run on rate hikes.

Amidst inflation which mortgage to chose?

Two 14-year-old boys dead following single-vehicle crash in Alberta

Two 14-year-old boys dead following single-vehicle crash in Alberta
RCMP in Alberta say two 14-year-old boys have died in a single-vehicle crash. Police say the crash happened Friday just southwest of Hinton. RCMP Const. Kelsey Davidge says there were three youths — all under 18 — in the vehicle at the time of the crash.

Two 14-year-old boys dead following single-vehicle crash in Alberta

A dozen B.C. communities surpass daily heat record

A dozen B.C. communities surpass daily heat record
A dozen communities in British Columbia surpassed their daily heat record Saturday, with the Quesnel area beating a record set in 1919. Records from Environment Canada show temperatures hit 23 C on Saturday, exceeding the old record set for that day of 22.2 C.

A dozen B.C. communities surpass daily heat record

Canadians stuck in Israel as flights are cancelled, embassy closed for Thanksgiving

Canadians stuck in Israel as flights are cancelled, embassy closed for Thanksgiving
Some Canadians said they were stuck in Israel amid deadly fighting Sunday, as airlines cancelled flights out of the country and reaching the Canadian Embassy on a holiday weekend proved difficult. Global Affairs Canada, meanwhile, said in a statement Sunday afternoon that it was aware of reports of one Canadian who has died amid the fighting and two others who are missing.

Canadians stuck in Israel as flights are cancelled, embassy closed for Thanksgiving

Three killed in small plane crash near Chilliwack, B.C., airport

Three killed in small plane crash near Chilliwack, B.C., airport
Three people have been killed in a small plane crash in Chilliwack, B.C. RCMP say in a statement they received a report that a plane had gone down at about 2 p.m. on Friday, not far from the airport in Chilliwack, about 100 kilometres east of Vancouver. 

Three killed in small plane crash near Chilliwack, B.C., airport

B.C. Mountie charged after crash in which motorcyclist was badly injured

B.C. Mountie charged after crash in which motorcyclist was badly injured
A Metro Vancouver RCMP officer has been charged under the Motor Vehicle Act after an off-duty crash in which a motorcyclist was seriously hurt.  The BC Prosecution Service says Const. Brendan Prasad faces a single charge of driving without due care and attention. 

B.C. Mountie charged after crash in which motorcyclist was badly injured