What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

RCMP say no critical injuries in crash of B.C. bus carrying pipeline camp workers

RCMP say no critical injuries in crash of B.C. bus carrying pipeline camp workers
Prince George RCMP say no critical injuries have been reported among the 30 people on the bus that went off a forest service road and crashed 120 kilometres north of Prince George, B.C.

RCMP say no critical injuries in crash of B.C. bus carrying pipeline camp workers

Pregnant woman at Surrey Memorial Hospital told to go home and wait, delivered baby in car

Pregnant woman at Surrey Memorial Hospital told to go home and wait, delivered baby in car
According to media reports, on Sunday, a pregnant woman gave birth to her baby in her car after being turned away from the hospital on the pretext that what she was experiencing wasn't labour pain. Doctors at the SMH gave her morphine and told her to go home and wait.

Pregnant woman at Surrey Memorial Hospital told to go home and wait, delivered baby in car

Impaired Abbotsford driver makes their child blow into the ignition interlock system

Impaired Abbotsford driver makes their child blow into the ignition interlock system
Police in Abbotsford say a driver admitted to making their child blow into the ignition interlock system meant to keep impaired drivers from getting behind the wheel. They’ve also informed the Ministry of Children and Family Development. 

Impaired Abbotsford driver makes their child blow into the ignition interlock system

Environment Canada says 10 tornadoes confirmed in Alberta during Wednesday storm

Environment Canada says 10 tornadoes confirmed in Alberta during Wednesday storm
Environment Canada confirms what it calls a "tornado outbreak" in rural Alberta earlier this week. It says between 2:30 p.m. and 7:30 p.m. on Wednesday, nine twisters hopscotched between Calgary and Medicine Hat and another was spotted near Vermillion in eastern Alberta. 

Environment Canada says 10 tornadoes confirmed in Alberta during Wednesday storm

Surrey to stay with RCMP over municipal force

Surrey to stay with RCMP over municipal force
The B.C. government recommended in April that Surrey continue its transition to the independent Surrey Police Service, offering $150 million over five years to help the city cover costs, but saying it would not pay the estimated $72 million in severance for officers if council decided to revert back to the RCMP.

Surrey to stay with RCMP over municipal force

B.C.'s largest wildfire still threatens, as conditions elsewhere ease

B.C.'s largest wildfire still threatens, as conditions elsewhere ease
Rain and cooler weather over much of British Columbia has prompted two fire centres in the southern and central Interior to roll back campfire bans. The Kamloops and Cariboo fire centres say the Category 1 open fire ban will lift at noon Friday, covering blazes no larger than 1.5-metres high by 1.5-metres wide. 

B.C.'s largest wildfire still threatens, as conditions elsewhere ease