What delayed Alberta carbon capture project: analysts

Darpan News Desk The Canadian Press, 03 May, 2024 10:45 AM
  • What delayed Alberta carbon capture project: analysts

 

Capital Power's decision not to pursue its $2.4-billion Genesee project is unlikely to be the first of other such cancellations, said Scott MacDougall of the Pembina Institute, a clean energy think tank.

"I think (Genesee) is different enough that I wouldn't extrapolate too much," MacDougall said.

But Sara Hastings-Simon, who studies energy transition at the University of Calgary, said the backtracking underlines that, unlike some decarbonization strategies, carbon capture adds cost.

"When some people say this is going to be a big part of our decarbonization solution, the question is who's going to pay for it." 

And Thomas Timmins, head of energy practice for the law firm Gowling WLG, called Capital Power's decision a reminder that carbon capture technology is still new.

"It is not where the proponents of the technology might wish it were," Timmins said.

Carbon capture separates climate-changing gases such as carbon dioxide from exhaust and sequesters it deep underground. Industries from cement manufacture to the oilsands consider it one of the most promising ways to reduce their carbon emissions.  

Capital Power announced Wednesday it would no longer pursue carbon capture at its Genesee power plant near Edmonton because the economics no longer work. 

The decision removed Canada's largest such project from the books. Genesee would have stored three million tonnes of carbon dioxide a year -- about three times the storage rate of Shell's Quest project. 

In a conference call with analysts Wednesday, Capital Power CEO Avik Dey said the technology has a future. 

"I do feel strongly that carbon capture and sequestration works," he said.

But several factors convinced the company to pull the plug -- the uncertainty over how much Capital Power could earn from the carbon credits the project would generate, the amount of carbon price it would avoid and the cost per tonne of the captured carbon.

"I wouldn't say it's any one thing," he said. "We need all of it to work.

"What will unlock carbon capture and storage for natural gas is the (cost per unit of carbon) coming down such that we can work within whatever regulatory framework exists. We're just early."

Capital Power would have been the first natural gas plant to use the technology. That creates risks and adds costs, MacDougall said. 

"There would be some extra costs relative to the second or third project. Costs will come down for future deployments."

The process is better understood in other applications, he said.

"(Carbon capture) on gas turbines is quite different than (carbon capture) on gas boilers."

Another risk is that other carbon capture projects planned for Alberta could flood the market for the credits carbon capture would generate, lowering their value. 

Hastings-Simon said Alberta could address that risk by tightening up its industrial carbon emissions program. 

Making credits harder to earn would ensure their continuing value, she said. So would increasing the market by lowering emissions caps for other industries. 

"If you're willing to do that as a government, you can pretty much control that risk."

Governments can also guarantee companies an adequate floor price for the carbon credits they generate. 

But failing a groundbreaking technological innovation, Timmins said carbon capture will continue to need public support for projects to go ahead.

"It hasn't reached the level where it's commercially viable, yet," Timmins said. 

"What's needed? Either a breakthrough or government money."

 

MORE National ARTICLES

RCMP say 15 dead after bus carrying seniors collides with semi truck Manitoba

RCMP say 15 dead after bus carrying seniors collides with semi truck Manitoba
Assistant Commissioner Rob Hill, the commanding officer of Manitoba's RCMP, said Thursday the crash happened at the intersection of highways 1 and 5 near Carberry, about two hours south of Dauphin.

RCMP say 15 dead after bus carrying seniors collides with semi truck Manitoba

Arrest made in Surrey stabbing

Arrest made in Surrey stabbing
On November 22nd of last year at approximately 12:08 p.m., the Surrey RCMP responded to a report of a stabbing outside of Tamanawis Secondary School. Officers located an 18-year old, later identified as Mehakpreet Sethi of Surrey, suffering life-threatening injuries. On Wednesday, as a result of advancements in the ongoing investigation, IHIT arrested a 17 year old suspect in relation to the murder of Mr. Sethi.  

Arrest made in Surrey stabbing

Burnaby's SFU campus behind picket lines

Burnaby's SFU campus behind picket lines
A statement on the S-F-U website says pickets were at several locations and it advised students with classes or labs in any of the affected buildings to check with their instructors or teaching assistants about possible disruptions.

Burnaby's SFU campus behind picket lines

Trans-Canada Highway closed, crews respond to crash in western Manitoba

Trans-Canada Highway closed, crews respond to crash in western Manitoba
RCMP have posted on social media that they are on the scene of a very serious collision near the intersection of Highway 1 and Highway 5. The STARS air ambulance service says it has been dispatched to the scene.

Trans-Canada Highway closed, crews respond to crash in western Manitoba

Drop in housing starts in Vancouver

Drop in housing starts in Vancouver
Canada Mortgage and Housing Corporation says housing starts in Vancouver tumbled 45 per cent in May. The drop covered all types of projects -- from apartments and condos to other kinds of multi-unit developments -- and the trend was reflected in Montreal, where starts were off 35 per cent, and in Toronto, where starts fell 28 per cent.

Drop in housing starts in Vancouver

Ottawa confirms land expropriations for rail bypass after Lac-Mégantic tragedy

Ottawa confirms land expropriations for rail bypass after Lac-Mégantic tragedy
Ottawa released a statement Wednesday confirming that it was going ahead with the expropriations without the consent of all affected land owners. Federal Transport Minister Omar Alghabra and Procurement Minister Helena Jaczek say in the release that the federal government will take physical possession of the parcels of land required for the project on Aug. 1.  

Ottawa confirms land expropriations for rail bypass after Lac-Mégantic tragedy