  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Union vote on Canada Post contract offer set to wrap up Friday afternoon

Union vote on Canada Post contract offer set to wrap up Friday afternoon
Voting is set to wrap up at 5 p.m., with results expected to be shared shortly after.

Union vote on Canada Post contract offer set to wrap up Friday afternoon

Premiers Smith, Moe disappointed by Trump's tariffs but most exports remain duty-free

Premiers Smith, Moe disappointed by Trump's tariffs but most exports remain duty-free
Saskatchewan Premier Scott Moe says the Canada-United States-Mexico trade agreement remains in place, allowing 95 per cent of his province's exports to move into the United States tariff-free. 

Premiers Smith, Moe disappointed by Trump's tariffs but most exports remain duty-free

Alberta company fined $210K in death of worker who fell through roof

Alberta company fined $210K in death of worker who fell through roof
The province says the worker had been replacing a building's metal roof near Mildred Lake, north of Edmonton, in 2023.

Alberta company fined $210K in death of worker who fell through roof

Transport committee meeting to study BC Ferries' $1B loan for Chinese ships

Transport committee meeting to study BC Ferries' $1B loan for Chinese ships
The House of Commons transport committee launched a study of the Canada Infrastructure Bank loan today.

Transport committee meeting to study BC Ferries' $1B loan for Chinese ships

Number of active wildfires in B.C. jumps to 120, with half started in last 24 hours

Number of active wildfires in B.C. jumps to 120, with half started in last 24 hours
The BC Wildfire Service said Friday that half of the fires had been started since late Wednesday as lightning storms swept across the province. 

Number of active wildfires in B.C. jumps to 120, with half started in last 24 hours

Carney disappointed after Trump hits Canada with 35 per cent tariffs

Carney disappointed after Trump hits Canada with 35 per cent tariffs
"While we will continue to negotiate with the United States on our trading relationship, the Canadian government is laser focused on what we can control: building Canada strong," Carney said in a media statement released just after midnight.

Carney disappointed after Trump hits Canada with 35 per cent tariffs