BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Canada Post rejects union's request for binding arbitration to end labour dispute

Canada Post rejects union's request for binding arbitration to end labour dispute
Canada Post has rejected a request from the union representing about 55,000 of its workers to send their ongoing labour dispute to binding arbitration.

Canada Post rejects union's request for binding arbitration to end labour dispute

Carney discusses "partnerships" with oil and gas executives in Calgary

Carney discusses
Prime Minister Mark Carney sat down with oil and gas executives in Calgary Sunday to discuss partnerships and to get their input for his plans to make Canada an energy superpower.

Carney discusses "partnerships" with oil and gas executives in Calgary

Joly commits to prioritizing Canadian steel, aluminum for defence, infrastructure

Ottawa is committed to using Canadian steel and aluminum in national infrastructure and defence projects as U.S. President Donald Trump threatens to impose more tariffs, Industry Minister Mélanie Joly said Sunday.

Joly commits to prioritizing Canadian steel, aluminum for defence, infrastructure

Ottawa collects extra $617M from import duties in March as counter-tariffs hit U.S.

Ottawa collects extra $617M from import duties in March as counter-tariffs hit U.S.
Ottawa collected an extra $617 million in import duties this past March compared to a year earlier as counter-tariffs against U.S. trade restrictions came into effect.

Ottawa collects extra $617M from import duties in March as counter-tariffs hit U.S.

Vancouver mayor, city councillors to meet with federal officials in Ottawa

Vancouver mayor, city councillors to meet with federal officials in Ottawa
The City of Vancouver says Mayor Ken Sim and two city councillors will travel to Ottawa this week to meet with senior federal officials.

Vancouver mayor, city councillors to meet with federal officials in Ottawa

B.C. pushes back on Alberta's pipeline pitch as premiers, PM meet in Saskatoon

B.C. pushes back on Alberta's pipeline pitch as premiers, PM meet in Saskatoon
British Columbia is pushing back against Alberta Premier Danielle Smith's proposal for a bitumen pipeline to B.C.'s northern coast.

B.C. pushes back on Alberta's pipeline pitch as premiers, PM meet in Saskatoon