BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Carney 'welcomes' U.S. court ruling striking down some U.S. tariffs

Carney 'welcomes' U.S. court ruling striking down some U.S. tariffs
Prime Minister Mark Carney said he "welcomes" the decision by the U.S. Court of International Trade to strike down President Donald Trump's broad-based tariffs on most countries.

Carney 'welcomes' U.S. court ruling striking down some U.S. tariffs

B.C. NDP ex-minister urges Eby to walk back 'astounding and disheartening' Bill 15

B.C. NDP ex-minister urges Eby to walk back 'astounding and disheartening' Bill 15
Former British Columbia minister Melanie Mark is accusing Premier David Eby and his cabinet of "turning their backs" on First Nations, local governments and environmentalists by passing controversial bills to fast-track infrastructure projects.

B.C. NDP ex-minister urges Eby to walk back 'astounding and disheartening' Bill 15

Ottawa police arrest 13 anti-war protesters demonstrating against arms show

Ottawa police arrest 13 anti-war protesters demonstrating against arms show
Ottawa Police say officers arrested 13 protesters on charges of mischief and assaulting police after they held demonstrations against an arms expo in the capital.

Ottawa police arrest 13 anti-war protesters demonstrating against arms show

Hockey players' trial hears interviews two accused gave to police in 2018

Hockey players' trial hears interviews two accused gave to police in 2018
The sexual assault trial of five former members of Canada's world junior hockey team is hearing interviews two of the accused gave to police months after the encounter with the complainant.

Hockey players' trial hears interviews two accused gave to police in 2018

National chief says First Nations frustrated by 'fast-track' approach to development

National chief says First Nations frustrated by 'fast-track' approach to development
The national chief of the Assembly of First Nations says she doesn't blame First Nations leaders who are voicing frustration with governments promising to fast-track development in their territories in the name of national unity.

National chief says First Nations frustrated by 'fast-track' approach to development

Trump's former secretary of state says Canadian sovereignty not under threat

Trump's former secretary of state says Canadian sovereignty not under threat
McGuinty said some countries are "doing away with national holidays" — a reference to Denmark's recent decision to abolish a long weekend holiday called "Great Prayer Day" in an attempt to bring in more tax revenue to cover its NATO defence spending target.

Trump's former secretary of state says Canadian sovereignty not under threat