BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Poilievre finds himself a spectator as debate gets underway in Parliament

Poilievre finds himself a spectator as debate gets underway in Parliament
Pierre Poilievre is in the unfamiliar position of watching the House of Commons as it gets underway today, instead of participating in the debate as he did for more than 20 years.

Poilievre finds himself a spectator as debate gets underway in Parliament

Court orders B.C. to pass law giving French school board expropriation powers

Court orders B.C. to pass law giving French school board expropriation powers
The B.C. Supreme Court has ordered the provincial government to pass a law within six months providing the Francophone School Board with powers to expropriate private property to build new French-language schools.

Court orders B.C. to pass law giving French school board expropriation powers

Canadian doctors group challenging constitutionality of Alberta transgender law

Canadian doctors group challenging constitutionality of Alberta transgender law
A group representing Canada's doctors is challenging the constitutionality of Alberta's legislation limiting access to medical treatment for transgender youth, arguing it violates their Charter right to freedom of conscience.

Canadian doctors group challenging constitutionality of Alberta transgender law

Human smuggler sentenced to 6 1/2 years in case of frozen family

Human smuggler sentenced to 6 1/2 years in case of frozen family
A judge in Minnesota has sentenced Steve Shand to 6 1/2 years for his role in a human smuggling operation that saw a family freeze to death in southern Manitoba near the Canada-U.S. border.

Human smuggler sentenced to 6 1/2 years in case of frozen family

Edmonton school trustees, advocates want province to allow undocumented kids to enrol

Edmonton school trustees, advocates want province to allow undocumented kids to enrol
Edmonton public school trustees have voted to push Alberta's government to make legislative changes to allow undocumented kids to enrol in school.

Edmonton school trustees, advocates want province to allow undocumented kids to enrol

Canada Post puts forward ‘final offers’ to union as overtime ban continues

Canada Post puts forward ‘final offers’ to union as overtime ban continues
Canada Post on Wednesday laid out its "final offers" to the union representing 55,000 workers after negotiations resumed Wednesday morning, as tensions run high over the future of the beleaguered institution.

Canada Post puts forward ‘final offers’ to union as overtime ban continues