BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Liberals win 4th mandate as NDP vote collapses and Singh announces he will resign

Liberals win 4th mandate as NDP vote collapses and Singh announces he will resign
On the final full day of the campaign, all major party leaders paused to address a deadly vehicle attack at a Filipino community event in Vancouver that took the lives of at least 11 attendees, leaving more injured in hospital.

Liberals win 4th mandate as NDP vote collapses and Singh announces he will resign

Conservative Leader Pierre Poilievre loses his long-held seat in Ottawa

Conservative Leader Pierre Poilievre loses his long-held seat in Ottawa
The Canadian Press decision desk is projecting that Conservative Leader Pierre Poilievre has lost in the Ottawariding of Carleton.

Conservative Leader Pierre Poilievre loses his long-held seat in Ottawa

Father, mother, five-year-old daughter, killed in Vancouver attack, leave son behind

Father, mother, five-year-old daughter, killed in Vancouver attack, leave son behind
Richard Le sent a text to his 16-year-old son on Saturday at about 8 p.m., saying he and the teen's stepmother and little sister would soon leave the Lapu Lapu Day festival inVancouver.

Father, mother, five-year-old daughter, killed in Vancouver attack, leave son behind

Alberta Premier Smith congratulates Carney, warns him against future 'hostile acts'

Alberta Premier Smith congratulates Carney, warns him against future 'hostile acts'
Alberta Premier Danielle Smith has delivered a note of congratulations — along with a sharply worded warning and a blanket condemnation — to Prime Minister Mark Carney and his new Liberal government.

Alberta Premier Smith congratulates Carney, warns him against future 'hostile acts'

B.C. to hold an independent commission into festival attack, considers public inquiry

B.C. to hold an independent commission into festival attack, considers public inquiry
British Columbia Premier David Eby says his government will launch an independent commission into the Vancouver festival attack that killed 11 people and a public inquiry if the criminal case doesn't provide answers the public is looking for. 

B.C. to hold an independent commission into festival attack, considers public inquiry

Man dies after car jumps curb, crashes into seven vehicles in Surrey, B.C.

Man dies after car jumps curb, crashes into seven vehicles in Surrey, B.C.
A man has died in a crash involving eight vehicles in Surrey, B.C., after he suffered what investigators believe to be a medical emergency while driving.

Man dies after car jumps curb, crashes into seven vehicles in Surrey, B.C.