BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Elections Canada says more than 19.5M voters cast a ballot in federal election

Elections Canada says more than 19.5M voters cast a ballot in federal election
Elections Canada says more than 68 per cent of eligible voterscast a ballot in the federal election — more than 19.5 million people.

Elections Canada says more than 19.5M voters cast a ballot in federal election

Winnipeg councillor, son of former Manitoba premier dead: mayor says

Winnipeg councillor, son of former Manitoba premier dead: mayor says
A Winnipeg city councillor who was the son of a formerManitoba premier and governor general of Canada has died.

Winnipeg councillor, son of former Manitoba premier dead: mayor says

Event planners across Canada rethinking security practices following Vancouver attack

Event planners across Canada rethinking security practices following Vancouver attack
Event organizers across Canada say they're combing over their security practices in the wake of Saturday night's deadly attack on a Vancouver street festival, hoping to fill any gaps to protect attendees.

Event planners across Canada rethinking security practices following Vancouver attack

Festival suspect had mental health team, no sign he needed hospitalization: ministry

Festival suspect had mental health team, no sign he needed hospitalization: ministry
The man accused of killing 11 people at a Vancouver festivalwas under the care of a mental health team, but there was nothing to indicate a change in his condition that warranted involuntarily hospitalization, British Columbia’s HealthMinistry said Tuesday. 

Festival suspect had mental health team, no sign he needed hospitalization: ministry

'It was all consensual,' woman says in video shown at hockey players' trial

'It was all consensual,' woman says in video shown at hockey players' trial
Holding a white towel against her body, a young woman smiles and looks into the camera.

'It was all consensual,' woman says in video shown at hockey players' trial

Economy shrunk 0.2% in February, StatCan estimates 1.5% annualized growth for Q1

Economy shrunk 0.2% in February, StatCan estimates 1.5% annualized growth for Q1
The Canadian economy shrunk in February, but economists say bad weather was likely the larger culprit than uncertainty related to the trade war with the U.S.

Economy shrunk 0.2% in February, StatCan estimates 1.5% annualized growth for Q1