BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Vancouver festival attack suspect to appear in court on Friday

Vancouver festival attack suspect to appear in court on Friday
The suspect in the street festival attack that killed 11 people in Vancouver will appear in provincial court in the city onFriday, just hours before a memorial mass to pray for the victims of the tragedy.

Vancouver festival attack suspect to appear in court on Friday

Day of mourning in B.C. as Vancouver festival attack suspect to face court

Day of mourning in B.C. as Vancouver festival attack suspect to face court
Premier David Eby says it's time for British Columbia to give back to the Filipino community on a day of remembrance and mourning for victims of the deadly attack on the Lapu Lapu Day festival in Vancouver, and  "take steps to ensure such an atrocity never happens again."

Day of mourning in B.C. as Vancouver festival attack suspect to face court

Wildfire prompts evacuations in Fort St. John, B.C., city says

Wildfire prompts evacuations in Fort St. John, B.C., city says
Firefighters from Fort St. John, B.C., and the provincial wildfireservice were battling a blaze that prompted evacuations late Thursday, the city said.

Wildfire prompts evacuations in Fort St. John, B.C., city says

Montreal men plead guilty after keeping woman's body on couch for six months

Montreal men plead guilty after keeping woman's body on couch for six months
Two Montreal men have pleaded guilty to committing an indignity to a body after admitting they left the remains of an Indigenous woman on the couch in their home for sixmonths. 

Montreal men plead guilty after keeping woman's body on couch for six months

Carney says he won't make a pact with NDP, confirms King Charles to launch Parliament

Carney says he won't make a pact with NDP, confirms King Charles to launch Parliament
King Charles will visit Ottawa to deliver the speech from the throne at the end of this month, Prime Minister Mark Carneysaid Friday.

Carney says he won't make a pact with NDP, confirms King Charles to launch Parliament

Prime Minister Carney to meet with U.S. President Trump in Washington on Tuesday

Prime Minister Carney to meet with U.S. President Trump in Washington on Tuesday
Prime Minister Mark Carney said Friday he will meet with U.S. President Donald Trump at the White House on Tuesday. 

Prime Minister Carney to meet with U.S. President Trump in Washington on Tuesday