BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Over 2 million Ninja-branded pressure cookers are recalled after reports of serious burn injuries

Over 2 million Ninja-branded pressure cookers are recalled after reports of serious burn injuries
NEW YORK (AP) — SharkNinja is recalling more than 2 millionpressure cookers sold in the U.S. and Canada — afterconsumers reported over 100 burn injuries spanning from a hazard that can cause hot food to spew out.

Over 2 million Ninja-branded pressure cookers are recalled after reports of serious burn injuries

B.C. gives short-term rental platforms an extension to confirm listings are legal

B.C. gives short-term rental platforms an extension to confirm listings are legal
The British Columbia government has granted short-termrental platforms an extra month to confirm their listings arelegal.

B.C. gives short-term rental platforms an extension to confirm listings are legal

Some Conservative MPs voice support for Poilievre as party stays silent on next moves

Some Conservative MPs voice support for Poilievre as party stays silent on next moves
Some Conservative MPs are expressing support for partyleader Pierre Poilievre after he lost both the federal election and his own seat on Monday.

Some Conservative MPs voice support for Poilievre as party stays silent on next moves

TransLink to expand Metro Vancouver bus service with newly approved investment plan

TransLink to expand Metro Vancouver bus service with newly approved investment plan
Metro Vancouver's transportation authority says a plan is in place to fund the largest increase in bus service in the region since 2018, in addition to expansions and improvements approved last year.

TransLink to expand Metro Vancouver bus service with newly approved investment plan

Elections Canada to investigate voting barriers in Nunavik

Elections Canada to investigate voting barriers in Nunavik
Elections Canada says it will investigate "shortcomings" that prevented some people in Nunavik from casting their vote inMonday's federal election. 

Elections Canada to investigate voting barriers in Nunavik

Bruce Fanjoy, retired businessman, says he defeated Poilievre by listening to voters

Bruce Fanjoy, retired businessman, says he defeated Poilievre by listening to voters
Bruce Fanjoy says he achieved something unexpected in Monday's election — the defeat of a high-profile Conservative leader in his own riding — simply by showing up on doorsteps and paying attention to what voters in Carleton were telling him.

Bruce Fanjoy, retired businessman, says he defeated Poilievre by listening to voters