BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

B.C. operation by police, regulators finds losses of $4M in assets to crypto fraud

B.C. operation by police, regulators finds losses of $4M in assets to crypto fraud
British Columbia's securities regulator says a recent two-day operation to identify victims of a specific type of cryptocurrency fraud has found 89 people who were drained of more than $4 million in assets.

B.C. operation by police, regulators finds losses of $4M in assets to crypto fraud

Party leaders face off in English for second federal leaders' debate

Party leaders face off in English for second federal leaders' debate
The leaders of Canada's four main political parties will square off for a second and final leaders' debate tonight in Montreal, after an initial French-language faceoff on Wednesday.

Party leaders face off in English for second federal leaders' debate

Draft budget plan proposes deep cuts across federal health programs

Draft budget plan proposes deep cuts across federal health programs
Though it's preliminary, the document gives an indication of the Trump administration’s priorities as it prepares its 2026 fiscal year budget proposal to Congress. The document indicates plans to deepen job and funding reductions across much of the federal government.

Draft budget plan proposes deep cuts across federal health programs

Woman, two young children missing after trying to cross border into Canada: RCMP

Woman, two young children missing after trying to cross border into Canada: RCMP
The RCMP say a woman and two young children are missing in the woods near the Quebec border with the United States after they were part of a group attempting to cross into Canada.

Woman, two young children missing after trying to cross border into Canada: RCMP

Supreme Court of Canada clarifies treatment of student loan debt under bankruptcy law

Supreme Court of Canada clarifies treatment of student loan debt under bankruptcy law
In 2013, she made a consumer proposal under the Bankruptcy and Insolvency Act, an alternative to bankruptcy that allows for payment of a portion of money owed, or payment over an extended perio

Supreme Court of Canada clarifies treatment of student loan debt under bankruptcy law

Alberta pauses some of its fight-back plan against the U.S. amid tariff dispute

Alberta pauses some of its fight-back plan against the U.S. amid tariff dispute
Alberta Premier Danielle Smith's government is pausing the procurement policy it announced more than a month ago to fight U.S. President Donald Trump's tariffs.

Alberta pauses some of its fight-back plan against the U.S. amid tariff dispute