BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Poilievre outlines plan to boost apprenticeships, training for trades workers

Poilievre outlines plan to boost apprenticeships, training for trades workers
Conservative Leader Pierre Poilievre announced a plan Friday to boost training and employment for workers in the skilled trades. Speaking at a news conference in Ottawa Friday morning, Poilievre said his plan for "more boots, less suits" will expand training halls and provide direct grants and faster access to employment insurance for apprentices in licensed trades.

Poilievre outlines plan to boost apprenticeships, training for trades workers

Several Canadian flights cancelled after London fire caused power outage at Heathrow

Several Canadian flights cancelled after London fire caused power outage at Heathrow
Several arriving and departing flights between cities across Canada and London's Heathrow Airport were cancelled after an overnight fire caused a power outage and forced the British airport to close Friday, with further flight disruptions expected to last for days. As of early Friday, Toronto's Pearson airport listed at least five scheduled arriving flights from Heathrow as cancelled, as well as two departing flights. Airports in Vancouver and Montreal also listed multiple cancelled flights.

Several Canadian flights cancelled after London fire caused power outage at Heathrow

Feds give millions to B.C.'s STEMCELL Technologies and HTEC for facility construction

Feds give millions to B.C.'s STEMCELL Technologies and HTEC for facility construction
The Ministry of Innovation, Science and Industry says North Vancouver-based HTEC, a hydrogen energy firm, is getting $49 million toward a facility that turns "industrial byproduct hydrogen" into fuel. 

Feds give millions to B.C.'s STEMCELL Technologies and HTEC for facility construction

Mark Carney will maintain oil and gas emissions cap, environment minister says

Mark Carney will maintain oil and gas emissions cap, environment minister says
Environment Minister Terry Duguid says a Mark Carney government will maintain a cap on oil and gas production emissions. In an interview with The Canadian Press, Duguid says Canada wants the energy but not the pollution that comes with its production.

Mark Carney will maintain oil and gas emissions cap, environment minister says

In latest blow to Tesla, regulators recall nearly all Cybertrucks

In latest blow to Tesla, regulators recall nearly all Cybertrucks
The National Highway Traffic Safety Administration's recall, which covers more than 46,000 Cybertrucks, warned that an exterior panel that runs along the left and right sight of the windshield can detach while driving, creating a dangerous road hazard for other drivers, increasing the risk of a crash.

In latest blow to Tesla, regulators recall nearly all Cybertrucks

Federal government commits $187M to rebuild critical infrastructure in Jasper

Federal government commits $187M to rebuild critical infrastructure in Jasper
More financial support is on the way for fire-ravaged Jasper, Alta., as the federal government has announced $187 million in new funding for the town's rebuild. It is the largest funding package to be announced since a runaway wildfire ripped through Jasper National Park and destroyed a third of the town last July.

Federal government commits $187M to rebuild critical infrastructure in Jasper