BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Confused about Mark Carney's blind trust? Here's how they work

Confused about Mark Carney's blind trust? Here's how they work
Prime Minister Mark Carney's critics have been asking pointed questions lately about the assets in the former central banker's blind trust — a tool meant to allow politicians to avoid conflicts of interest. How do blind trusts work?

Confused about Mark Carney's blind trust? Here's how they work

B.C. Greens want answers about New Democrats' emergency powers legislation

B.C. Greens want answers about New Democrats' emergency powers legislation
Interim Leader Jeremy Valeriote said in a statement that while he understands the "urgency of the situation" given the ongoing trade strife with the United States, the proposed Bill 7 in its current form has "vague wording" and "could allow for sweeping economic decisions without clear limits or transparency."

B.C. Greens want answers about New Democrats' emergency powers legislation

Poilievre wants 'shovel ready zones' with pre-approved construction permits

Poilievre wants 'shovel ready zones' with pre-approved construction permits
Conservative Leader Pierre Poilievre wants to create what he calls "shovel ready zones" that would have pre-approved permits for major projects resources or energy projects. In a media statement, Poilievre says that the goal is to permits in place for a mine, liquefied natural gas plant, pipeline or other major project. 

Poilievre wants 'shovel ready zones' with pre-approved construction permits

Federal union concerned about planned cuts to Translation Bureau

Federal union concerned about planned cuts to Translation Bureau
A major federal union says it's worried about a plan to eliminate more than 300 positions at Canada’s Translation Bureau. In a news release, the Canadian Association of Professional Employees says it’s condemning a five-year business plan that would shrink the bureau’s workforce by almost 25 per cent.

Federal union concerned about planned cuts to Translation Bureau

Prime Minister Mark Carney expected to call federal election on Sunday

Prime Minister Mark Carney expected to call federal election on Sunday
Prime Minister Mark Carney is expected to launch a federal election campaign on Sunday and send Canadians to the polls as soon as April 28. While sources would not confirm the date of the vote, federal campaigns must run at least 37 days.

Prime Minister Mark Carney expected to call federal election on Sunday

Bank of Canada signals shift in how it sets rates amid tariff uncertainty

Bank of Canada signals shift in how it sets rates amid tariff uncertainty
Tiff Macklem says that means monetary policymakers may be “acting quickly” when it comes to setting interest rates, rather than looking far into the horizon to stay “flexible and adaptable.”

Bank of Canada signals shift in how it sets rates amid tariff uncertainty