BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Federal government promises $2.55B in low-cost loans to build Toronto rental homes

Federal government promises $2.55B in low-cost loans to build Toronto rental homes
The federal government is promising billions in low-cost financing to help build thousands of rental homes in Toronto, including more than a thousand affordable units. Ottawa says it will provide $2.55 billion in financing through its Apartment Construction Loan Program, to be administered by the Canada Mortgage and Housing Corporation.

Federal government promises $2.55B in low-cost loans to build Toronto rental homes

Statistics Canada says population rose to 41,528,680 at Jan. 1 as growth slowed

Statistics Canada says population rose to 41,528,680 at Jan. 1 as growth slowed
Statistics Canada says the population grew to 41,528,680 people as of Jan. 1 as the pace of growth continued to slow after peaking in the third quarter of 2023. The total number of people was up 63,382 compared with Oct. 1, 2024, for a quarterly growth rate of 0.2 per cent.

Statistics Canada says population rose to 41,528,680 at Jan. 1 as growth slowed

Poilievre says Trump is right to say a Liberal PM would be easier to deal with

Poilievre says Trump is right to say a Liberal PM would be easier to deal with
Conservative Leader Pierre Poilievre says U.S. President Donald Trump is right to think he would have an easier time dealing with a Liberal prime minister in Canada. On Fox News on Tuesday evening, Trump was asked about the upcoming election and the fact that polls now suggest the Liberals are in the lead.

Poilievre says Trump is right to say a Liberal PM would be easier to deal with

Safety board to release preliminary report on Delta plane crash in Toronto

Safety board to release preliminary report on Delta plane crash in Toronto
The Transportation Safety Board of Canada says it will release a preliminary report Thursday on a crash landing at Toronto's Pearson airport that sent 21 people to hospital last month. The Delta Air Lines flight arriving from Minneapolis crashed on Feb. 17, leading to days of travel disruptions at Canada's busiest airport.

Safety board to release preliminary report on Delta plane crash in Toronto

Prime Minister Mark Carney set to host meeting with Canada's premiers Friday

Prime Minister Mark Carney set to host meeting with Canada's premiers Friday
Prime Minister Mark Carney is hosting a meeting with Canada's premiers on Friday. The prime minister's office and the office of Ontario Premier Doug Ford confirmed details of the meeting. 

Prime Minister Mark Carney set to host meeting with Canada's premiers Friday

Vancouver International Auto Show removes Tesla, citing safety concerns at event

Vancouver International Auto Show removes Tesla, citing safety concerns at event
The Vancouver International Auto Show says it has removed Tesla from participating in this week's event over safety concerns.  Executive Director Eric Nicholl says the show asked the electric carmaker to withdraw because of a "primary concern" for the safety of workers, attendees and exhibitors.

Vancouver International Auto Show removes Tesla, citing safety concerns at event