BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

North Vancouver RCMP arrest a man who claimed to be a police officer

North Vancouver RCMP arrest a man who claimed to be a police officer
Mounties in North Vancouver say they've arrested a man for impersonating an officer and they believe there may be more than one victim.  Police have released a photo of a dark grey Ford F-150 that they say was seized when the driver was arrested earlier this month, and they're asking if anyone else was pulled over by the truck. 

North Vancouver RCMP arrest a man who claimed to be a police officer

B.C. doles out grant funding to bolster food manufacturing sector

B.C. doles out grant funding to bolster food manufacturing sector
Jobs Minister Diana Gibson says money from the province's manufacturing jobs fund will go to seven B.C. companies, including $2 million to Kelowna-based Farming Karma Fruit Co. for a new processing facility and equipment.

B.C. doles out grant funding to bolster food manufacturing sector

Mountain biking groups 'stretched thin' with trail work as popularity grows

Mountain biking groups 'stretched thin' with trail work as popularity grows
The outdoors were a refuge for many during the pandemic as people hit their local trail networks to mountain bike, hike, run and walk, but advocates in British Columbia say the value of trails isn't reflected in the level of support they receive. Deanne Cote, executive director of the North Shore Mountain Bike Association, said no one could have anticipated the surge in people using the local trails.

Mountain biking groups 'stretched thin' with trail work as popularity grows

Conservatives say there will be no media seats on Poilievre's election campaign

Conservatives say there will be no media seats on Poilievre's election campaign
The Conservative party is breaking from tradition and will not be allowing media onboard planes and buses for Pierre Poilievre's election campaign. In an email Tuesday, national campaign director Jenni Byrne says costs for travel have "risen considerably," as has the capacity for digital and remote access to public events.

Conservatives say there will be no media seats on Poilievre's election campaign

Liberals lagging well behind other parties on nominating candidates as election looms

Liberals lagging well behind other parties on nominating candidates as election looms
With a federal election call expected any day now, the Liberal party is trailing well behind its rivals on nominating candidates. The Conservatives have nominated 275 candidates out of 343 ridings, the NDP has 217 candidates and the Green Party has 208 — but the Liberal party has so far nominated just 185 candidates.

Liberals lagging well behind other parties on nominating candidates as election looms

Audit finds B.C.'s forest management hurt by flawed data without clear methodology

Audit finds B.C.'s forest management hurt by flawed data without clear methodology
The Office of the Auditor General of B.C. says in the report that defined methodologies to calculate forest carbon projections were not used for decisions such as the determining annual allowable timber cutting. 

Audit finds B.C.'s forest management hurt by flawed data without clear methodology