BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

AHS confirms cases of measles in Edmonton, public exposure possible in two locations

AHS confirms cases of measles in Edmonton, public exposure possible in two locations
Alberta Health Services says it has confirmed multiple cases of measles in the Edmonton area. An advisory issued by the health authority Sunday warns that public exposure to the highly contagious disease may have occurred at two Edmonton locations last week.

AHS confirms cases of measles in Edmonton, public exposure possible in two locations

Former prime minister Brian Mulroney to be featured on Canada Post stamp

Former prime minister Brian Mulroney to be featured on Canada Post stamp
Former prime minister Brian Mulroney will be featured on a stamp as part of Canada Post's 2025 lineup. Mulroney, who died last year, served as prime minister from 1984 to 1993.

Former prime minister Brian Mulroney to be featured on Canada Post stamp

Carney, Macron launch new bilteral partnership on intelligence and security

Carney, Macron launch new bilteral partnership on intelligence and security
Carney and Macron discussed a new bilateral partnership on intelligence and security, focused on enhancing cybersecurity and sharing intelligence on "significant threats," the Prime Minister's Office said in a statement about the conversation.

Carney, Macron launch new bilteral partnership on intelligence and security

B.C. hydro rates to increase in 2025, 2026 but remain among lowest in North America

B.C. hydro rates to increase in 2025, 2026 but remain among lowest in North America
Adrian Dix says the government will be submitting a "rate stability direction" to the B.C. Utilities Commission for approval of a BC Hydro rate increase of 3.75 per cent on April 1 and for the same bump next year.

B.C. hydro rates to increase in 2025, 2026 but remain among lowest in North America

Quebec aluminum towns aren’t feeling the sting of 25 per cent U.S. tariffs

Quebec aluminum towns aren’t feeling the sting of 25 per cent U.S. tariffs
Layoffs aren't expected at Aluminerie Alouette in Sept-Îles, Que., a major aluminum producer with some 950 employees, says the town's mayor, Denis Miousse. The company, which describes itself as the biggest aluminum smelter on the continent, can find new export markets if demand weakens in the U.S.

Quebec aluminum towns aren’t feeling the sting of 25 per cent U.S. tariffs

Carney’s move to kill carbon price now official but debate over it not dead

Carney’s move to kill carbon price now official but debate over it not dead
Prime Minister Mark Carney's move Friday to end the consumer carbon price has done little to put the long-standing political battle to rest. Rather, Carney's theatrical document signing led to another heated debate about whether the paper he signed was even a real thing.

Carney’s move to kill carbon price now official but debate over it not dead