BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Carney says his government starts in a moment of crisis in Canada-U.S. relations

Carney says his government starts in a moment of crisis in Canada-U.S. relations
Mark Carney was sworn in as Canada's 24th prime minister in a ceremony at Rideau Hall on Friday morning, along with a leaner Liberal cabinet that he said is focused on "meeting the moment" and facing down the threat posed by U.S. President Donald Trump. In his first press conference as prime minister, Carney said his government will concentrate on growing the economy, making life more affordable and making the country more secure.

Carney says his government starts in a moment of crisis in Canada-U.S. relations

Five things to know about Prime Minister Mark Carney's new cabinet

Five things to know about Prime Minister Mark Carney's new cabinet
Mark Carney was sworn in Friday as Canada's 24th prime minister in a ceremony in Rideau Hall, alongside his new cabinet. Here are five things to know about the new prime minister's plans and his new cabinet.

Five things to know about Prime Minister Mark Carney's new cabinet

RCMP arrest suspects in shooting in Penticton, B.C.

RCMP arrest suspects in shooting in Penticton, B.C.
Mounties in Penticton say they've arrested the final two suspects in a shooting in the city earlier this month. No one was hurt in the shooting and police say one suspect was taken into custody immediately after the incident on March 6, but two other people escaped. 

RCMP arrest suspects in shooting in Penticton, B.C.

B.C. overdose deaths drop 30 per cent, but researchers point to 'emerging dangers'

B.C. overdose deaths drop 30 per cent, but researchers point to 'emerging dangers'
BC Coroners Service data show nearly half the people who died in January due to unregulated toxic drugs had the depressant bromazolam in their system, which researchers say highlights "emerging dangers" in the illicit drug supply even as deaths decline. The coroners service said Friday that 152 people died of toxic drug overdoses in January, marking four consecutive months that the toll was under 160.

B.C. overdose deaths drop 30 per cent, but researchers point to 'emerging dangers'

Reaction to Mark Carney being sworn in as prime minister

Reaction to Mark Carney being sworn in as prime minister
Mark Carney has been sworn in as Canada's new prime minister, succeeding Justin Trudeau. Here's how some leaders and politicians are reacting to his appointment.

Reaction to Mark Carney being sworn in as prime minister

Eby announces ending of provincial carbon tax, after Carney kills federal version

Eby announces ending of provincial carbon tax, after Carney kills federal version
Premier David Eby said at a news conference in Surrey that legislation is being prepared to repeal the consumer carbon tax during the current legislative session, with sittings scheduled to resume on March 31.

Eby announces ending of provincial carbon tax, after Carney kills federal version