BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Politics and sports set to collide as Canada, U.S. meet in 4 Nations final

Politics and sports set to collide as Canada, U.S. meet in 4 Nations final
Sports and politics will collide tonight in Boston as archrivals Canada and the United States compete in the final of the 4 Nations Face-Off. What might have been initially conceived as an exhibition international hockey tournament in advance of the NHL's return to Olympic competition in 2026 has turned into a must-watch event on both sides of the border due to political tension between the formerly friendly nations.

Politics and sports set to collide as Canada, U.S. meet in 4 Nations final

Feds list criminal organizations as terrorist entities to fight fentanyl trafficking

Feds list criminal organizations as terrorist entities to fight fentanyl trafficking
The federal government says seven transnational criminal organizations are being listed as terrorist entities under the Criminal Code to fight fentanyl trafficking. The move is the latest federal measure to bolster security in response to American criticism.

Feds list criminal organizations as terrorist entities to fight fentanyl trafficking

Old-growth logging was 'goal' of Interfor: B.C. Forest Appeals Commission decision

Old-growth logging was 'goal' of Interfor: B.C. Forest Appeals Commission decision
The commission issued the decision last week, upholding the finding that Interfor committed eight contraventions of the Forest and Range Practices Act with the logging between 2012 and 2016 in the Arrow Lakes area of southeastern B.C. The timber had a market value of about $4.4 million, and the estimated economic benefit was more than $1.8 million after subtracting the company's costs, it said.

Old-growth logging was 'goal' of Interfor: B.C. Forest Appeals Commission decision

Dr. Monty Ghosh: Shaping New Pathways in Addiction and Homelessness Care  

Dr. Monty Ghosh: Shaping New Pathways in Addiction and Homelessness Care  
Another catalytic project led by Dr. Ghosh is the National Overdose Response Service (NORS), a lifeline for individuals using substances alone. What began as an idea inspired by a patient’s innovative approach to virtual support has blossomed into a nationwide initiative. The emergency line aims to provide immediate support to people and ensure that they aren't using drugs alone.  

Dr. Monty Ghosh: Shaping New Pathways in Addiction and Homelessness Care  

Canadian Armed Forces says it's on track to meet this year's recruitment goal

Canadian Armed Forces says it's on track to meet this year's recruitment goal
More Canadians have expressed an interest in joining the military since U.S. President Donald Trump took office on Jan. 20 — but the Canadian Armed Forces isn't attributing that spike to Trump and his talk of annexing Canada.

Canadian Armed Forces says it's on track to meet this year's recruitment goal

Second case of measles confirmed in B.C.'s Lower Mainland, linked to Thailand flight

Second case of measles confirmed in B.C.'s Lower Mainland, linked to Thailand flight
Health authorities in British Columbia have confirmed a second case of measles in the Lower Mainland, this time in the Vancouver Coastal Health region. Vancouver Coastal Health says in a release that the infected person travelled to Southeast Asia in the same party as a Fraser Health region resident who tested positive earlier this month.

Second case of measles confirmed in B.C.'s Lower Mainland, linked to Thailand flight