British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Liberal leadership candidate Mark Carney plans 'small' deficits for capital projects

Liberal leadership candidate Mark Carney plans 'small' deficits for capital projects
Liberal leadership candidate Mark Carney is vowing to split the federal budget between capital and operating spending, and to balance the operating side while running small capital deficits. Carney made the comments at a press conference in Scarborough, Ont., where he also promised he would reduce the debt-to-GDP ratio over time.

Liberal leadership candidate Mark Carney plans 'small' deficits for capital projects

B.C. legislative assembly re-elects Raj Chouhan as its Speaker ahead of throne speech

B.C. legislative assembly re-elects Raj Chouhan as its Speaker ahead of throne speech
British Columbia's legislative session opens today amid what Premier David Eby describes as a time of "extraordinary change and uncertainty." Lt.-Gov. Wendy Cocchia is scheduled to deliver the speech from the throne this afternoon, laying out the B.C. government's plan as looming U.S. tariffs threaten the Canadian economy.

B.C. legislative assembly re-elects Raj Chouhan as its Speaker ahead of throne speech

Most of the injured in Pearson plane crash released from hospital as probe continues

Most of the injured in Pearson plane crash released from hospital as probe continues
Delta said in a social media post that 19 out of 21 passengers initially taken to Toronto-area hospitals have been released as the investigation continues. Delta flight 4819 from Minneapolis to Toronto, operated by subsidiary Endeavor Air, crashed on landing around 2:30 p.m. Monday. Flint said authorities will not speculate about a possible cause until a thorough investigation is complete. 

Most of the injured in Pearson plane crash released from hospital as probe continues

Seven male suspects sought in B.C. theft of more than $2,400 in fragrances

Seven male suspects sought in B.C. theft of more than $2,400 in fragrances
Police in Richmond are searching for seven suspects in an alleged retail theft of fragrances worth more than $2,400. RCMP say the theft took place on Nov. 11 of last year, when the seven men reportedly entered a store in the 3800 block of Steveston Highway.

Seven male suspects sought in B.C. theft of more than $2,400 in fragrances

Green Party says it will run full slate of candidates in coming federal election

Green Party says it will run full slate of candidates in coming federal election
The Green Party's leaders say they will have a full slate of candidates for the next election, which could be called as soon as next month. Party co-leader Elizabeth May said Tuesday the party is still vetting potential candidates but it expects to run someone in every federal riding.

Green Party says it will run full slate of candidates in coming federal election

After Trump pitches idea, Russian ambassador says Moscow not rejoining G7

After Trump pitches idea, Russian ambassador says Moscow not rejoining G7
Canada disagrees with U.S. President Donald Trump's suggestion that Russia rejoin the G7 — but Moscow says the idea is a non-starter anyway. Moscow's Ambassador to Canada Oleg Stepanov says "Russia has no interest" in joining the Group of Seven, which he calls an "outdated structure."

After Trump pitches idea, Russian ambassador says Moscow not rejoining G7