BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

First Nations group presses Ottawa to come back to the table for child welfare talks

First Nations group presses Ottawa to come back to the table for child welfare talks
The national chief of the Assembly of First Nations is asking for an update from the Caring Society months after chiefs put it and a newly formed committee in charge of seeking new negotiations with Canada, and after Canada informed the assembly it was only prepared to renegotiate with First Nations in Ontario.

First Nations group presses Ottawa to come back to the table for child welfare talks

Israel-Hamas ceasefire welcomed but protests in Canada will not stop, groups say

Israel-Hamas ceasefire welcomed but protests in Canada will not stop, groups say
While a ceasefire in the 15-month war is welcome news, "there will be no pauses, no breaks, no rests" in protests that have endured for more than a year, said Gur Tsabar, a spokesperson for the Jews Say No to Genocide coalition.

Israel-Hamas ceasefire welcomed but protests in Canada will not stop, groups say

Crash lands 2 children in hospital

Crash lands 2 children in hospital
Police in Whitehorse say two children are in hospital after a single-vehicle crash on Tuesday. R-C-M-P, the fire department, and emergency services responded to a crash involving one vehicle that hit the children while they were on bicycles.

Crash lands 2 children in hospital

Walmart Canada says underweight meat problem fixed by B.C. supplier

Walmart Canada says underweight meat problem fixed by B.C. supplier
Walmart, Sobeys and Loblaw Companies were hit with a class-action lawsuit last week alleging they "misrepresented" the weight of meat by including the weight of packaging in prices. Walmart Canada says in an emailed statement that a third-party supplier was responsible for an "isolated incident" at the Richmond store for a two-week period last month.

Walmart Canada says underweight meat problem fixed by B.C. supplier

'Water's away': How Canadian helicopters and waterbombers are helping tame L.A. fires

'Water's away': How Canadian helicopters and waterbombers are helping tame L.A. fires
British Columbia-based Coulson Aviation released the video of its crew "delivering a precision water drop on the Palisades Fire in California."  Coulson's helicopters as well as waterbombing planes provided by Quebec have played a high-profile role in the battle against the fires that have claimed at least 25 lives and destroyed thousands of homes.

'Water's away': How Canadian helicopters and waterbombers are helping tame L.A. fires

B.C. forests minister says Trump tariffs could be 'devastating' to sector

B.C. forests minister says Trump tariffs could be 'devastating' to sector
B.C.'s Forests Minister Ravi Parmar says U.S. softwood lumber duties and president-elect Donald Trump's threatened tariffs could be "devastating" to the province's forestry sector. He says the province needs to bring a "team B.C. and a team Canada" approach to fighting the duties.

B.C. forests minister says Trump tariffs could be 'devastating' to sector