BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Trudeau says he hopes Gaza ceasefire will 'turn down the temperature' in Canada

Trudeau says he hopes Gaza ceasefire will 'turn down the temperature' in Canada
Prime Minister Justin Trudeau is welcoming news of a ceasefire deal to pause the 15-month war in the Gaza Strip. He says he hopes the deal will "turn down the temperature" on tensions in Canada and rebuild strained relationships between people affected by the war.

Trudeau says he hopes Gaza ceasefire will 'turn down the temperature' in Canada

B.C. farmers challenge government order to cull ostrich herd over avian flu outbreak

B.C. farmers challenge government order to cull ostrich herd over avian flu outbreak
British Columbia ostrich farmers ordered to cull a herd of 400 due to an avian flu outbreak are holding onto hope that the Canadian Food Inspection Agency will change its mind before their kill date in just over two weeks.  The federal agency sent Universal Ostrich Farms Inc. a notice on Dec. 31 instructing their ostriches to be destroyed and disposed of by Feb. 1, but the owners are asking for more time to prove their farm should be spared. 

B.C. farmers challenge government order to cull ostrich herd over avian flu outbreak

First half of 5 lane Steveston interchange complete

First half of 5 lane Steveston interchange complete
B-C's Transportation Ministry says the first half of the new five-lane Steveston Interchange is now complete. Kelly Greene, M-L-A for Richmond-Steveston, says this marks a "major step" in improving transportation in the region, adding that once complete, it will improve connections between Highway 99 and the Steveston Highway.

First half of 5 lane Steveston interchange complete

Snowfall warning for Fort Nelson region

Snowfall warning for Fort Nelson region
Environment Canada has issued a snowfall warning for the Fort Nelson region. It says a Pacific frontal system will bring about 10 centimetres of snow starting this afternoon. The weather office says the snow will persist until tomorrow morning.

Snowfall warning for Fort Nelson region

Trudeau and the premiers meet to discuss a response to Trump's threatened tariffs

Trudeau and the premiers meet to discuss a response to Trump's threatened tariffs
Canada's premiers are set to meet with Prime Minister Justin Trudeau and members of his cabinet today to talk about U.S. president-elect Donald Trump's vow to impose steep tariffs. Trump has promised to impose 25 per cent tariffs on all Canadian and Mexican imports — one of several measures he says he'll enact on day one of his presidency through an executive order. He assumes that office on Monday.

Trudeau and the premiers meet to discuss a response to Trump's threatened tariffs

Ultrasound technician accused of sexually assaulting woman at Edmonton clinic

Ultrasound technician accused of sexually assaulting woman at Edmonton clinic
An ultrasound technician has been charged with sexually assaulting a patient at his southeast Edmonton clinic last year.  Edmonton police say 53-year-old Aasim Syed Ahmed was charged in August 2024 with one count of sexual assault.

Ultrasound technician accused of sexually assaulting woman at Edmonton clinic