BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Federal energy minister hails 'one project, one review' approval for B.C. LNG plant

Federal energy minister hails 'one project, one review' approval for B.C. LNG plant
Hodgson says the Ksi Lisims LNG project that received a B.C. environmental certificate on Monday, followed by federal approval, is an example of the "one project, one review" system in which the Canadian government relied on the province for an assessment.

Federal energy minister hails 'one project, one review' approval for B.C. LNG plant

Chrystia Freeland to leave cabinet for Ukraine envoy role: reports

Chrystia Freeland to leave cabinet for Ukraine envoy role: reports
Freeland joined Prime Minister Mark Carney's cabinet meeting this morning in Ottawa but blew past the TV cameras and did not answer any questions about her political future.

Chrystia Freeland to leave cabinet for Ukraine envoy role: reports

Third woman dies after stabbing in East Vancouver residential building

Third woman dies after stabbing in East Vancouver residential building
Fifty-four-year-old Viet Quy John Ly from Vancouver has already been charged with two counts of second-degree murder after the bodies of 55-year-old Jianghui Deng and Chunxiu Yin, 54, were found in a residential building near Joyce Street and Vanness Avenue.

Third woman dies after stabbing in East Vancouver residential building

B.C., federal governments support huge LNG facility, opposed by some First Nations

B.C., federal governments support huge LNG facility, opposed by some First Nations
A B.C. environmental assessment certificate for the Ksi Lisims LNG project that is designed to export Canadian gas to Asia was jointly approved on Monday by B.C. Environment Minister Tamara Davidson and B.C. Energy Minister Adrian Dix.

B.C., federal governments support huge LNG facility, opposed by some First Nations

B.C. debt and deficit balloon with carbon tax gone and growth slides

B.C. debt and deficit balloon with carbon tax gone and growth slides
The deficit is up largely due to the elimination of the carbon tax and amid "global trade uncertainty," Bailey said. 

B.C. debt and deficit balloon with carbon tax gone and growth slides

Five takeaways from the first day of the fall sitting of Parliament

Five takeaways from the first day of the fall sitting of Parliament
Federal Housing Minister Gregor Robertson said in response that the Liberals are partnering with the private sector and various levels of government to deliver affordable homes.

Five takeaways from the first day of the fall sitting of Parliament