BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Shooting in Surrey leaves man with serious but non-life-threatening injuries

Shooting in Surrey leaves man with serious but non-life-threatening injuries
Surrey police say the man was allegedly shot following an "altercation" between two groups at Bear Creek Park.

Shooting in Surrey leaves man with serious but non-life-threatening injuries

RCMP say four passengers dead in northern Manitoba plane crash

RCMP say four passengers dead in northern Manitoba plane crash
RCMP say their detachment in Island lake, Man., got a report on Saturday evening that a plane had crashed approximately 40 kilometres south of St. Theresa Point First Nation, near its destination of Makepeace Lake.

RCMP say four passengers dead in northern Manitoba plane crash

The budget, bail and other bills: Five things to watch for as Parliament returns

The budget, bail and other bills: Five things to watch for as Parliament returns
Prime Minister Mark Carney said Sunday that the deficit recorded in the budget will be bigger than it was last year, though he did not offer a specific number.

The budget, bail and other bills: Five things to watch for as Parliament returns

69-year-old woman dead after a two-vehicle collision in Delta, B.C., Sunday afternoon

69-year-old woman dead after a two-vehicle collision in Delta, B.C., Sunday afternoon
Police say they responded to the intersection of 116th Street and 77A Avenue following reports of a two-car collision at 12:20 p.m. 

69-year-old woman dead after a two-vehicle collision in Delta, B.C., Sunday afternoon

Elections Canada to launch review following issues with special ballots

Elections Canada to launch review following issues with special ballots
A report released by the chief electoral officer today says Elections Canada will examine its training, control mechanisms and processes.

Elections Canada to launch review following issues with special ballots

B.C. left out of housing announcement by Carney to build 4,000 units on federal lands

B.C. left out of housing announcement by Carney to build 4,000 units on federal lands
Carney said Sunday that the newly created Build Canada Homes agency will oversee plans to build 4,000 homes on six federally owned sites, but none of them are located in B.C. 

B.C. left out of housing announcement by Carney to build 4,000 units on federal lands