BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Majority of Canadian youth have been bullied, child poverty on the rise: report

Majority of Canadian youth have been bullied, child poverty on the rise: report
The Raising Canada report says more than 70 per cent of Canadian youth between the ages of 12 and 17 experienced bullying in the last year, and more than 13 per cent of children were living in poverty by the end of 2024.

Majority of Canadian youth have been bullied, child poverty on the rise: report

Ottawa sets 100-day timeline to fix CRA call centre delays

Ottawa sets 100-day timeline to fix CRA call centre delays
François-Philippe Champagne set the timeline in a letter to Liberal MP Karina Gould, chair of Parliament's finance committee, which was posted to his X account Tuesday morning.

Ottawa sets 100-day timeline to fix CRA call centre delays

Vancouver police investigate death of pedestrian who was struck by car

Vancouver police investigate death of pedestrian who was struck by car
The department says in a news release that first responders attempted to save the man's life but he died at the scene.

Vancouver police investigate death of pedestrian who was struck by car

Prime Minister Mark Carney huddles with cabinet in Toronto ahead of fall sitting

Prime Minister Mark Carney huddles with cabinet in Toronto ahead of fall sitting
Carney’s first cabinet retreat at Meech Lake in Quebec in May was a secretive, two-day postelection planning huddle.

Prime Minister Mark Carney huddles with cabinet in Toronto ahead of fall sitting

Muslim Community Care Foundation Hosts First-Ever Sister National Cup Tournament

Muslim Community Care Foundation Hosts First-Ever Sister National Cup Tournament
This groundbreaking tournament provided a platform for young Muslim women to showcase not only their athletic talents but also their leadership, teamwork, and passion for the game.

Muslim Community Care Foundation Hosts First-Ever Sister National Cup Tournament

StatCan to release GDP data for June and Q2 today

StatCan to release GDP data for June and Q2 today
The agency's early estimates for GDP in the second quarter had been for zero growth as trade uncertainty and tariffs weigh on business and consumer sentiment. 

StatCan to release GDP data for June and Q2 today