BC Hydro says it should have been more proactive as Site C costs overflowed

Darpan News Desk The Canadian Press, 04 Nov, 2025 10:00 AM
  • BC Hydro says it should have been more proactive as Site C costs overflowed

British Columbia's power utility says it should have been more proactive about ballooning costs on the massive Site C hydroelectric dam project, partly blaming a failure to budget for "low-probability, high-consequence risks."

BC Hydro says in a "lessons learned report" to the British Columbia Utilities Commission that it's on track to complete the project on the Peace River within a $16 billion budget.

But that's almost double the original 2014 budget of about $8.8 billion, which was increased twice, in 2018 and 2021.

BC Hydro blames the huge overrun on the pandemic, as well as a failure to budget for low-probability risks that included substantial geotechnical problems.

The utility says it should have "ramped up its internal project resources more proactively and sooner."

Site C is the third hydro dam on the Peace River in northeastern B.C. and it provides enough electricity to power about 450,000 homes every year. 

The 224-page report, submitted last Thursday, says future projects should better communicate the "breadth" of risks with the potential for significant impacts on budget and scheduling.

An executive summary says that "consistent with industry best practices" the methodology of the project’s cost-risk analysis meant that unlikely risks were excluded from the original budget. 

"Accordingly, the project contingency and project reserve were both insufficient to absorb the full costs when these high-consequence, low-probability risk events materialized."

It says that while the pandemic was "unforeseen," the potential geotechnical challenges were understood.

Enhancing the dam's right bank foundation accounted for $1.1 billion of the overall budget increase, left bank cracks accounted for $600 million, and construction delays caused by the COVID-19 pandemic accounted for $1.6 billion.

Further costs increases were related to contractor claims, redesigns, and other factors, it says. 

However, the report also says the challenges that sent the budget soaring were met with "ingenuity and determination."

"Overall, BC Hydro reflects on the Site C Project with pride and a commitment to learn and improve," the summary says.

Picture Courtesy: THE CANADIAN PRESS/Jonathan Hayward

MORE National ARTICLES

Law advocates slam Ottawa for silence on Trump sanctioning Canadian ICC judge

Law advocates slam Ottawa for silence on Trump sanctioning Canadian ICC judge
The U.S. State Department also sanctioned citizens of France, Fiji and Senegal over their role in the ICC's investigation of Israel's actions in Gaza and the West Bank.

Law advocates slam Ottawa for silence on Trump sanctioning Canadian ICC judge

Smith's Alberta Next panel hears cheers for deportation, separation in Lloydminster

Smith's Alberta Next panel hears cheers for deportation, separation in Lloydminster
Smith's panel, which is touring the province to hear from the public on ways to shield the province from federal overreach, drew a friendly crowd of about 350 to a public recreation centre Wednesday night.

Smith's Alberta Next panel hears cheers for deportation, separation in Lloydminster

Poll suggests 85% of Canadians want governments to regulate AI

Poll suggests 85% of Canadians want governments to regulate AI
The Leger poll found 85 per cent of respondents believe governments should regulate AI tools to ensure ethical and safe use. More than half, 57 per cent, said they strongly agreed with that statement.

Poll suggests 85% of Canadians want governments to regulate AI

Active wildfires jump as heat warnings continue for parts of B.C.

Active wildfires jump as heat warnings continue for parts of B.C.
BC Wildfire Service figures Thursday morning show 78 active blazes, up from 68 on Wednesday, with 16 new starts and eight fires declared out over the past 24 hours.

Active wildfires jump as heat warnings continue for parts of B.C.

Canada, India name new high commissioners, as both countries restore relations

Canada, India name new high commissioners, as both countries restore relations
Foreign Affairs Minister Anita Anand says Christopher Cooter will be Canada's new high commissioner to India.

Canada, India name new high commissioners, as both countries restore relations

Proposed changes in the Family Law Act to give more support to the families

Proposed changes in the Family Law Act to give more support to the families
The FLA is the main law that deals with family violence, guardianship, parenting duties, support payments and dividing property after a separation. The review looks at how the law can better reflect today's society and recent court decisions.

Proposed changes in the Family Law Act to give more support to the families