Saskatchewan's Boundary dam carbon capture project underperforms, report says

Darpan News Desk The Canadian Press, 02 May, 2024 01:13 PM
  • Saskatchewan's Boundary dam carbon capture project underperforms, report says

"We don't think carbon capture works as well as industry and promoters claim," said David Schissel, an analyst who wrote the report for the Institute for Energy Economics and Financial Analysis, an international non-profit agency.

"We don't think it's a good use of money to keep coal-fired power plants running."

Schissel looked at data from Sask Power's Boundary Dam project, a coal-fired power plant in southeast Saskatchewan that began capturing carbon dioxide emissions in the fall of 2014. 

Proponents originally said the plant would capture up to 90 per cent of the plant's carbon emissions. That would amount to about a million tonnes of climate-changing carbon dioxide a year — the rough equivalent of emissions from 200,000 cars.   

That goal has never been reached, said Schissel. 

When all the plant's emissions are factored in, including flue gas that is simply vented, the average capture rate is 57 per cent, he said.

A 2022 report delivered to an international conference on carbon capture backs up the findings. 

"(The project) has not sustained the design rate beyond a dedicated capacity demonstration completed in 2015," says the report from the International CCS Knowledge Centre in Regina. 

The report says capture is limited by both technical issues and the demand for carbon dioxide from the energy industry, which uses the gas to extract more oil from depleting reserves. 

The plant's capture rate has improved, although it's still short of the million-tonne mark.  

Knowledge Centre spokesman Grady Semmens said Schissel's analysis is "generally correct."

He said the plant has managed to keep nearly six million tonnes of carbon dioxide out of the atmosphere. As well, he said almost all the CO2 from the emissions that are sent through the capture facility is separated out.

"For a variety of technical and economic reasons ... the (Boundary Dam) facility has not been run at full capacity, which has impacted the overall volume of CO2 captured over the last 10 years," Semmens wrote in an email. "This does not mean the project has not been successful.

"It has provided valuable experience and lessons that we are now actively applying to the next generation of CCS projects."

SaskPower spokesman Scott McGregor said the facility continues to improve. He said the equipment was online for almost the entire first three months of 2024 — its best performance yet.

"The knowledge we’ve gained at our (carbon capture) facility has also made SaskPower a resource for development of (such) projects in a wide range of industries outside of power generation, such as cement manufacturing, oil and gas production and chemical processing," he said in an email.

But Schissel said to live up to advocates' promises, carbon capture has to work nearly perfectly all the time. 

"If you're going to try to reduce greenhouse gas emissions by capturing CO2, you've got to capture almost all the emissions and you've got to do it year in and year out for decades."

"Carbon capture hasn't done what its proponents claimed it would do."

Other carbon capture projects have yet to reach their stated goals.

Since 2015, Shell's Quest project near Edmonton has stored nine million tonnes of CO2 at a lower-than-anticipated cost. But its capture rate of 77 per cent remains below the 90 per cent originally announced.

On Wednesday, Capital Power CEO Avik Dey said the company would no longer pursue its $2.4-billion carbon capture project at its Genesee power plant.

"Fundamentally, the economics just don't work," he told analysts in a conference call. "Hopefully, the technology will improve, and we can revisit this when the economics improve.

"What it really is, is the technology improving so the costs come down. How do you actually build the kit so you have higher efficacy and capture rates while bringing down the capture costs?"

Alberta's oilsands producers have estimated the cost of the first phase of carbon capture for the industry at $16 billion. 

Schissel said carbon capture can be worthwhile in some circumstances, especially at a smaller scale. He said it remains questionable if the technology can work at the level proponents suggest and asks whether it's the most cost-effective way to reduce emissions at large operations.

"We may find out in 20 years that we didn't capture as much CO2 as we needed to and we wasted a lot of money that could have been better spent."

MORE National ARTICLES

Elections BC bans Mark Marissen and municipal party over financing breach

Elections BC bans Mark Marissen and municipal party over financing breach
A news release from the elections body says the party and six of its eight candidates in last year's municipal vote failed to meet the filing deadline for finance reports in January this year.  The agency says the party's campaign finance report also disclosed violations, including an improper $50,000 loan and prohibited donations.

Elections BC bans Mark Marissen and municipal party over financing breach

Busy Canada Day weekend for Prince George RCMP

Busy Canada Day weekend for Prince George RCMP
A statement from the detachment says officers were called to everything from robberies and attempted robberies to the torching of a vehicle -- possibly by a suspect already wanted on two other warrants.

Busy Canada Day weekend for Prince George RCMP

"A preoccupation with failure." Why the Titan submersible was doomed from the start

Jack Rozdilsky, a professor at York University in Toronto,  says OceanGate's business — ferrying paying passengers to the floor of the North Atlantic — could be compared to the immensely risky work of companies that launch space flights, drill for offshore oil, fight wildfires or operate nuclear power plants.

"A preoccupation with failure." Why the Titan submersible was doomed from the start

Joly concerned for safety of India's diplomats, calls protest poster 'unacceptable

Joly concerned for safety of India's diplomats, calls protest poster 'unacceptable
The poster is the latest in a string of problems in recent weeks that have increased tension between Ottawa and New Delhi over Sikh separatists in Canada. A poster for the event circulating on social media includes photos of India's top two diplomats in Canada — High Commissioner Sanjay Kumar Verma and Toronto Consul General Apoorva Srivastava — and refers to them as "the faces of Niijar's killers in Toronto."

Joly concerned for safety of India's diplomats, calls protest poster 'unacceptable

Prime Minister Justin Trudeau travelling to Latvia and NATO summit in Lithuania

Prime Minister Justin Trudeau travelling to Latvia and NATO summit in Lithuania
Prime Minister Justin Trudeau will travel to Europe next week for the annual NATO leaders' summit. The two-day summit in Lithuania starts July 11 and comes as the alliance has agreed to extend the term of Secretary-General Jens Stoltenberg by another year.  

Prime Minister Justin Trudeau travelling to Latvia and NATO summit in Lithuania

Several students stranded at Vancouver airport after Air India flight to Delhi cancelled

Several students stranded at Vancouver airport after Air India flight to Delhi cancelled
One of the students, speaking anonymously, stated, "On July 1, around 9 p.m., we received an email from Air India informing us of a five-hour delay, and the new departure time was set for 2.45 p.m. However, when we arrived at the airport, we discovered that the flight had been delayed for an additional hour."

Several students stranded at Vancouver airport after Air India flight to Delhi cancelled